HomeMy WebLinkAboutCapital Improvement Program Adopted FY 2014-2015Capital Improvement Program
Adopted FY 2014 -15
Planned FY 2015 -16 through
FY 2018 -19
City of Mountain View, California
Mission Statement:
The City of Mountain View provides quality services
and facilities that meet the needs of a caring and diverse
community in a financially responsible manner.
CITY OF MOUNTAIN VIEW
Capital Improvement Program
Adopted FY 2014 -15
Planned FY 2015 -16 through FY 2018 -19
City Council
Christopher R. Clark, Mayor
John McAlister, Vice Mayor
Margaret Abe -Koga
Ronit Bryant
John M. Inks
R. Michael Kasperzak, Jr.
Jac Siegel
Submitted by:
Daniel H. Rich, City Manager
Michael A. Fuller, Public Works Director
Linda Forsberg, Transportation and Business Manager
Prepared by:
Jerry Burgess, Senior Administrative Analyst
CITE' OF MOUNTAIN VIEW
MEMORANDUM
Public Works Department
DATE: September 14, 2014
TO: City Council
FROM: Jerry Burgess, Senior Administrative Analyst
Linda Forsberg, Transportation and Business Manager
Michael A. Fuller, Public Works Director
VIA: Daniel H. Rich, City Manager
SUBJECT: Adopted Fiscal Year 2014 -15 through 2018 -19 Capital Improvement
Program
The City Council provided guidance for the development of the Adopted Fiscal Year
2014 -15 through Fiscal Year 2018 -19 Capital Improvement Program (CIP) during Study
Sessions on March 18 and May 20, 2014, as well as a March 25, 2014 Study Session
focused on Park Land Dedication (PLD) Fee - funded capital projects.
The CIP was adopted by the City Council on June 17, 2014, and funding for Fiscal Year
2014 -15 projects was approved as part of the adoption of the Fiscal Year 2014 -15 budget
on June 17, 2014.
ADOPTED FISCAL YEAR 2014 -15 THROUGH FISCAL YEAR 2018 -19 CAPITAL
IMPROVEMENT PROGRAM
The Adopted Fiscal Year 2014 -15 through Fiscal Year 2018 -19 CIP is balanced and
maintains all fund reserves as required by Council policy.
PLD Funds will provide a significant degree of funding in the Adopted Five -Year CIP,
contributing $15 million to the design and construction of the Community Center and
approximately $4.0 million more to the design and construction of the 771 Rengstorff
Avenue and Fayette Drive Area Parks.
As detailed in Appendix 1 of this document, a significant amount of rehabilitation work
on the City's wastewater system is planned during the next five years. A funding
strategy to address these capital needs, as well as the costs the City will incur as a
partner in the Palo Alto Regional Water Quality Control Plant (PARWQCP) to
Adopted Fiscal Year 2014 -15 through 2018 -19 CIP
September 14, 2014
Page 2 of 3
rehabilitate and bring the 40- year -old facility to current regulatory and Best Practices
operating standards, was presented to the City Council during the April 29 Narrative
Budget Study Session. Sewer rates will be gradually increased during the next 10 fiscal
years to fund the costs of these long -term capital improvements.
Adopted Fiscal Year 2013 -14 Capital Projects
New Projects
In addition to funding 26 planned nondiscretionary annual and periodic infrastructure
maintenance projects to preserve the City's significant investment in its infrastructure
and facilities, the Adopted Fiscal Year 2014 -15 through 2018 -19 CIP funds 23 new
discretionary projects responding to City Council and community priorities. Funding
for one of the nondiscretionary annual projects, Water System Improvements, has been
increased by $200,000 in each of the five years of the CIP to accelerate the installation of
remote -read water meters. Additional information regarding the Water Meter
Replacement Plan is provided in Appendix 2 of this document.
Additional information regarding each of the new nondiscretionary and discretionary
projects can be found in the Nondiscretionary Projects and Discretionary Projects
sections of this document.
Amended Projects
The Adopted Fiscal Year 2014 -15 through 2018 -19 CIP also includes funding
amendments to eight existing capital projects reflecting changes to project scopes
and /or funding requirements. Additional information regarding project amendments
is available in the Amendments to Existing Projects section of this document.
Appendix 3 of this document includes additional detail regarding funding
enhancements approved for three existing Information Technology (IT) related projects
(Projects 08 -18, 10 -18, and 12 -18). Also included is a description of the new IT- related
initiatives that will be undertaken and funded by the Fiscal Year 2014 -15 annual
nondiscretionary IT project, Project 15 -18. Additional funding for IT projects was
approved as part of the Fiscal Year 2014 -15 CIP to support the Council's goal of using
technology to enhance customer service, efficiency, and advance the mission of the
organization.
Adopted Fiscal Year 2014 -15 through 2018 -19 CIP
September 14, 2014
Page 3 of 3
Outer -Year Planned Projects
Years 2 through 5 of the Adopted Five -Year CIP include a limited number of new
nondiscretionary and discretionary projects added to the outer years of the CIP and
timing adjustments to projects previously scheduled to occur in the outer years of the
CIP. Information regarding planned outer -year capital projects is provided in the
Nondiscretionary and Discretionary Projects sections of this document.
Unscheduled Projects
The Unscheduled Projects section of this document provides a list of projects that were
not programmed into the Five -Year CIP because of funding limitations and /or their
lower - priority status as compared to other projects. Additional information regarding
one of the unscheduled projects, US -27, Library Remodel, Construction, can be found in
Appendix 4 of this document.
Active Projects and Projects to Close
Staff carefully reviewed the status of all active capital projects to determine which
projects could be closed at the end of Fiscal Year 2013 -14 so that unspent balances could
be reprogrammed to other capital projects. This effort resulted in $1.9 million being
returned to various funding sources. A list of the remaining active projects is provided
in the Active Projects section of this document.
A list of projects closed at the end of the 2013 -14 fiscal year is provided in the Projects to
Close section of this document.
CONCLUSION
The Adopted Fiscal Year 2014 -15 through Fiscal Year 2018 -19 CIP places a priority on
funding annual and periodic infrastructure projects that preserve the City's significant
investment in infrastructure and facilities, and new projects that support City Council
and community priorities.
JB- LF -MAF/ 3/ PSD
791- 09- 14 -14M -E
Adopted FY 2014 -15 and Planned FY 2015 -16 through FY 2018 -19
Non - Discretionary Projects
All numbers are in thousands (1,000)
Brief descriptions and funding sources for the projects below are provided on the pages indicated.
Pro j .
No.
Non - Discretionary Projects
Budget
Page
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
xx -O 1
Street Resurfacing Program
$ 861
$ 879
$ 897
$ 914
$ 932
1
xx -02
Traffic and Streetlight Improvements
302
322
341
349
356
1
xx -03
Slurry Seal Program
126
129
131
134
137
1
xx -04
Water System Improvements
533
544
555
566
577
2
xx -05
Wastewater System Improvements
149
152
155
158
162
2
xx -06
Concrete Sidewalk/Curb Repairs
287
293
299
305
311
2
xx -07
Parks Pathway Resurfacing
78
79
81
82
84
3
xx -08
Shoreline Pathway, Roadway, Parking Improvements
184
187
191
195
199
3
xx -09
Forestry Maintenance Program & Street Tree Replanting
299
305
311
317
323
3
xx -10
Shoreline Landfill Cap Maintenance and Repairs
126
129
131
134
137
4
xx -11
Developer Reimbursements
116
116
120
120
124
4
xx -12
Street Lane Line and Legend Repainting
416
54
363
56
378
4
xx -13
Landfill Gas /Leachate System Repairs & Improvements
126
129
131
134
137
5
xx -14
Facilities Maintenance Plan
517
527
538
549
559
5
xx -15
Annual Traffic Studies/NTMP Improvements
126
129
131
134
137
5
xx -16
Maintenance Agreement for JPB /VTA Transit Center
57
59
60
61
62
6
xx -17
Shoreline Infrastructure Maintenance
230
234
239
244
249
6
xx -18
Information Technology Computer Projects
1,011
527
538
550
560
6
xx -19
Biennial Park Renovations /Improvements
103
108
112
7
xx -19
Biennial Median Renovations and Roadway Landscape
Renovations
70
73
7
xx -20
Biennial Good Neighbor Fence Replacements
34
36
37
7
xx -20
Biennial Real Estate Technical and Legal Services
71
73
7
xx -21
Miscellaneous Water Main/Service Line Replacement
2,165
2,415
2,465
2,515
2,565
8
xx -22
Miscellaneous Storm/Sanitary Sewer Main Replacement
1,495
1,525
1,555
1,585
1,615
8
xx -23
TDA Projects
180
60
60
60
60
8
xx -24
Biennial ADA Improvements to City Facilities
86
90
93
9
xx -24
Biennial Installation of ADA Curb Ramps
62
64
9
xx -25
Annual New Energy Conservation Measures
172
88
179
91
187
9
xx -26
Biennial Tennis Court Resurfacing
80
84
87
9
xx -26
Biennial PMP Recertification
69
72
10
xx -27
Traffic Signal Replacements (Location TBD)
379
387
394
402
10
Total: Non - Discretionary Projects
$ 9,859
$ 9,533
$ 10,176
$ 9,929
$ 10,582
Non - Discretionary Projects
All numbers are in thousands (1,000)
Project xx -01 Sponsor Department: Public Works Department
Street Resurfacing Program Category: Streets and Sidewalks
Install asphalt concrete and fog seal overlays, g
raise utilities and monuments. Additional Annual None Prevailing Wage Yes
O &M Costs: Project?
Funding Sources
Project Number and Fiscal Year
15 -01 16 -01 17 -01 18 -01 19 -01
2014 -15 2015 -16 2016 -17 2017 -18 2018 -19
Public Works Department
Total
C/C Tax
Gas Tax
Shoreline Community
$ 80
$ 82
738
$ 84
753
60
$ 85 $ 87
768 783
61 62
$ 418
3,766
299
724
57
59
Total
$ 861
$ 879
$ 897
$ 914
$ 932
$ 4,483
Project xx -02
Sponsor Department:
Public Works Department
Traffic and Street Light Improvements
Category:
Traffic, Parking and Transportation
Replace traffic signal controllers, traffic detector
loops, back -up batteries, LED traffic signal lights,
Additional Annual
None Prevailing Wage
TBD
radar speed signs, and street light poles. Includes
O &M Costs:
Project?
minor modifications to existing traffic signals to
improve traffic safety.
Project Number and Fiscal Year
15 -02 16 -02
17 -02 18 -02 19 -02
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
C1C Tax
$ 276
$ 295
$ 312
$ 319
$ 326
$ 1,528
Shoreline Community
26
27
29
30
30
142
Total
$ 302
$ 322
$ 341
$ 349
$ 356
$ 1,670
Project xx -03 Sponsor Department: Public Works Department
Slurry Seal Program Category: Streets and Sidewalks
Apply slurry seal to selected street surfaces and g
City facility parking lots as required. Additional Annual None Prevailing Wage Yes
O &M Costs: Project?
Project Number and Fiscal Year
15 -03 16 -03 17 -03 18 -03 19 -03
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
C1C Tax $ 126 $ 129 $ 131 $ 134 $ 137 $ 657
Total $ 126 $ 129 $ 131 $ 134 $ 137 $ 657
Page 1
Non - Discretionary Projects
All numbers are in thousands (1,000)
Project xx -04 Sponsor Department: Public Works Department
Water System Improvements Category: Utilities
Scheduled replacement of water system g ry
components and minor unscheduled Additional Annual None Prevailing Wage TBD
improvements to the City's water system. O &M Costs: Project?
Funding Sources
Project Number and Fiscal Year
Public Works Department
15 -04
16 -04
17 -04
18 -04
19 -04
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Water Fund
$ 533
$ 544
$ 555
$ 566
$ 577
$ 2,775
Total
$ 533
$ 544
$ 555
$ 566
$ 577
$ 2,775
Project xx -05
Sponsor Department:
Public Works Department
15 -06
Wastewater System Improvements
Category:
g n
Utilities
19 -06
2014 -15
Unscheduled improvements /repairs to the City's
2016 -17
2017 -18
2018 -19
Total
wastewater collection and pumping system.
Additional Annual
None
Prevailing Wage
TBD
$ 311
O &M Costs:
Total
Project?
$ 293
$ 299 $ 305 $ 311
Project Number and Fiscal Year
15 -05 16 -05
17 -05
18 -05 19 -05
Funding Sources
2014 -15 2015 -16
2016 -17
2017 -18 2018 -19
Total
Wastewater Fund
$ 149
$ 152
$ 155
$ 158
$ 162
$ 776
Total
$ 149
$ 152
$ 155
$ 158
$ 162
$ 776
Project xx -06
Concrete Sidewalk/Curb Repairs
Replace deteriorated sidewalks and repair
concrete curbs, gutters, and sidewalks displaced
by street tree growth, and/or failure of City -
owned utilities.
Sponsor Department: Public Works Department
Category: Streets and Sidewalks
Additional Annual None Prevailing Wage Ye
O &M Costs: Project?
Funding Sources
Project Number and Fiscal Year
15 -06
16 -06
17 -06
18 -06
19 -06
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
C/C Tax
$ 287
$ 293
$ 299
$ 305
$ 311
$ 1,495
Total
$ 287
$ 293
$ 299 $ 305 $ 311
1 $ 1,495
Page 2
Non - Discretionary Projects
All numbers are in thousands (1,000)
Project xx -07 Sponsor Department: Community Services Department
Parks Pathway Resurfacing Category: Parks and Recreation
Renovate various park pathways within City g ry
parks. Additional Annual None Prevailing Wage TBD
O &M Costs: Project?
Project Number and Fiscal Year
15 -07 16 -07 17 -07 18 -07 19 -07
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
C/C Tax $ 78 $ 79 $ 81 $ 82 $ 84 $ 404
Total $ 78 $ 79 $ 81 $ 82 $ 84 $ 404
Project xx -08
Sponsor Department:
Community Services Department
Shoreline Pathway, Roadway, Parking
Category:
g ry
Parks and Recreation
Improvements
Correct drainage problems and damage due to
Additional Annual
None Prevailing Wage
TBD
differential settlement; provide pathway, roadway
O &M Costs:
Project?
and parking related improvements.
Project Number and Fiscal Year
15 -08 16 -08
17 -08 18 -08 19 -08
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
Shoreline Community
$ 184
$ 187
$ 191 $ 195
$ 199
$ 956
Total
$ 184
$ 187
$ 191 $ 195
$ 199
$ 956
Project xx -09
Forestry Maintenance Program and Street
Tree Replanting
Contract to prune, remove, stump, purchase and
plant approximately 800 to 1,000 medium to
large trees within the City. Maintain trees
damaged by freezing, disease, drought and other
natural causes.
FundinLy Sources
(` /(` T.-
Total
Sponsor Department: Community Services Department
Category: Parks and Recreation
Additional Annual None Prevailing Wage TBD
O &M Costs: Project?
Project Number and Fiscal Year
15 -09 16 -09 17 -09 18 -09 19 -09
2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 kTotal
$ 299 $ 305 $ 311 $ 317 $ 323 $ 1,555
$ 299 $ 305 $ 311 $ 317 $ 323 $ 1,555
Page 3
Non - Discretionary Projects
All numbers are in thousands (1,000)
Project xx -10
Sponsor Department:
Public Works Department
16 -11
Shoreline Landfill Cap Maintenance and
Category:
Regulatory Requirements
Repairs
2015 -16
2016 -17
2017 -18
Regulatory mandates of the Bay Area Air Quality
Additional Annual
None Prevailing Wage
TBD
Management District and the Regional Water
O &M Costs:
Project?
29
Quality Control Board require the City to protect
31
149
29
the integrity of the landfill cap and prevent
30
30
31
surface emissions by regrading, filling,
Project Number and Fiscal Year
29
recompacting, and making other improvements.
30
31
149
$ 116
$ 116
$ 120
$ 120
15 -10
16 -10
17 -10
18 -10
19 -10
Funding Sources
2014 -15
2015 -16
2016 -17 2017 -18
2018 -19
Total
Solid Waste
$ 126
$ 129
$ 131
$ 134
$ 137
$ 657
Total
$ 126
$ 129 $ 131 $ 134 $ 137
$ 657
Project xx -11
Developer Reimbursements
Construction of street and utility improvements
concurrent with private development. Adjacent
properties benefiting from street and utility
improvements will be required to reimburse the
City for the improvements.
FundinLy Sources
C/C Tax
Water Fund
Wastewater Fund
Storm Water Fund
Total
Project xx -12
Street Lane Line and Legend Repainting
Annual repainting of City street lane lines and
legends.
Sponsor Department: Public Works Department
Category: Miscellaneous
Additional Annual Prevailing Wage
O &M Costs: None Project? No
Project Number and Fiscal Year
15 -11
16 -11
17 -11
18 -11
19 -11
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
$ 29
$ 29
$ 30 $ 30
30 30
$ 31
$ 149
29
29
31
149
29
29
30
30
31
149
29
29
30
30
31
149
$ 116
$ 116
$ 120
$ 120
$ 124
$ 596
Sponsor Department: Public Works Department
Category: Streets and Sidewalks
Additional Annual None Prevailing Wage yes
O &M Costs: Project?
Project Number and Fiscal Year
15 -12 16 -12 17 -12 18 -12 19 -12
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
C/C Tax $ 416 $ 54 $ 363 $ 56 $ 378 $ 1,267
Total $ 416 $ 54 $ 363 $ 56 $ 378 $ 1,267
Page 4
Non - Discretionary Projects
All numbers are in thousands (1,000)
Project xx -13
Landfill Gas/Leachate System Repairs and
Improvements
Annual repairs and improvements to large
components of the landfill gas and leachate
system.
Waste
Total
Fundinu Sources
Sponsor Department: Public Works Department
Category: Regulatory Requirements
Additional Annual None Prevailing Wage TBD
O &M Costs: Project?
Project Number and Fiscal Year
15 -13 16 -13 17 -13 18 -13 19 -13
2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
$ 126 $ 129 $ 131 $ 134 $ 137 $ 657
$ 126 $ 129 $ 131 $ 134 $ 137 $ 657
Project xx -14
Sponsor Department:
Public Works Department
Annual Traffic Studies/NTMP Improvements
Facilities Maintenance Plan
Category:
Facilities
Repair, replace, or maintain City facilities
Additional Annual
None Prevailing Wage TBD
conformance with the Neighborhood Traffic
O &M Costs:
(HVAC, roofs, carpets, plumbing, etc.).
Additional Annual
None
Prevailing Wage
TBD
O &M Costs:
with neighborhood traffic issues.
Project?
Project Number and Fiscal Year
Project Number and Fiscal Year
15 -15
16 -15
15 -14 16 -14
17 -14
18 -14 19 -14
Funding Sources
2014 -15 2015 -16
2016 -17
2017 -18 2018 -19
Total
C/C Tax
$ 402
$ 410
$ 418
$ 427
$ 435
$ 2,092
Shoreline Community
115
117
120
122
124
598
Total
$ 517
$ 527
$ 538
$ 549
$ 559
$ 2,690
Project xx -15
Sponsor Department:
Public Works Department
Annual Traffic Studies/NTMP Improvements
Category:
Traffic, Parking and Transportation
Funding for traffic calming devices on
neighborhood, local, and residential streets in
Additional Annual
None Prevailing Wage TBD
conformance with the Neighborhood Traffic
O &M Costs:
Project?
Management Program, and annual contracts with
traffic consultants to assist the Traffic Section
with neighborhood traffic issues.
Project Number and Fiscal Year
15 -15
16 -15
17 -15
18 -15
19 -15
Funding Sources
2014 -15
2015 -16
2016 -17 2017 -18
2018 -19
Total
C/C Tax
$ 126
$ 129
$ 131
$ 134
$ 137
$ 657
Total
$ 126 $ 129 $ 131
$ 134
$ 137
$ 657
Page 5
Non - Discretionary Projects
All numbers are in thousands (1,000)
Project xx -16 Sponsor Department: Public Works Department
Maintenance Agreement for JPB/VTA Transit Category: Facilities
Center g
Reimbursement of City expenses by JPB /VTA. Additional Annual None Prevailing Wage No
O &M Costs: Project?
Project Number and Fiscal Year
15 -16 16 -16 17 -16 18 -16 19 -16
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Other (Reimbursement) $ 57 $ 59 $ 60 $ 61 $ 62 $ 299
Total $ 57 $ 59 $ 60 $ 61 $ 62 $ 299
Project xx -17 Sponsor Department: Public Works Department
Shoreline Infrastructure Maintenance Category: Utilities
Maintenance of water lines, sewer lines, storm g
drainage system, and water system supplying the Additional Annual None Prevailing Wage TBD
sailing lake. O &M Costs: Project?
Project Number and Fiscal Year
15 -17 16 -17 17 -17 18 -17 19 -17
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Shoreline Community $ 230 $ 234 $ 239 $ 244 $ 249 $ 1,196
Total $ 230 $ 234 � $ 239 $ 244 $ 249 1 $ 1,196
Project xx -18
Information Technology Computer Projects
For descriptions of the amendments to the various
information technology computer projects, please
see the information technology memorandum
included in this document.
Sponsor Department: Information Technology
Category: Information Technology and
g Communications
Additional Annual None Prevailing Wage No
O &M Costs: Project?
Funding Sources
Project Number and Fiscal Year
15 -18 16 -18 17 -18 � 18 -18 19 -18
2014 -15 15 -16 2016 -17 � 2017 -18 2018 -19
Total
C/C Tax
Water Fund
Wastewater Fund
Solid Waste
$ 572
$ 375
$ 382 $ 390 $ 398
42 43 44
42 43 44
36 37 37
36 37 37
- - -
- - -
$ 2,117
121
41
291
105
41
275
163
243
13
84
18
35
Shoreline Community
Development Services
Equipment Replacement (Fleet Internal Services)
98
13
84
35
-
-
Total
$ 1,011
$ 527 $ 538 $ 550 $ 560
$ 3,186
Page 6
Non - Discretionary Projects
All numbers are in thousands (1,000)
Projects 15 -19, 17 -19 & 19 -19
Sponsor Department:
Community Services Department
Biennial Park Renovations /Improvements
Category:
g ry
Parks and Recreation
Biennial repairs and improvements to City parks.
Category:
Miscellaneous
Funding for appraisals, environmental reports,
Additional Annual
Prevailing Wage
Projects 16 -19 & 18 -19
O &M Costs:
None
Project?
TBD
Biennial Median Renovations and Roadway
O &M Costs:
None Project?
No
Landscape Renovations
Project Number and Fiscal Year
Biennial repairs and improvements to City
Project Number and Fiscal Year
landscaped medians and roadway landscaping.
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
C/C Tax
$ -
$ 18
$ -
15 -19
16 -19
17 -19
18 -19
19 -19
8
Funding Sources
2014 -15
2015 -16
2016 -17 2017 -18
2018 -19
Total
GC Tax
$ 103
$ 70
$ 108
$ 73
$ 112
$ 466
Total
$ 103
$ 70
$ 108 $ 73 $__1_1_2F$_466
Projects 15 -20, 17 -20 & 19 -20 Sponsor Department: Community Services Deparhnent
Biennial Good Neighbor Fence (GNF) Category: Parks and Recreation
Replacements g rY
Funding to replace fencing between City parks Additional Annual None Prevailing Wage No
and private property. O &M Costs: Project?
Project Number and Fiscal Year
15 -20 17 -20 19 -20
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
C/C Tax $ 34 $ - $ 36 $ - $ 37 $ 107
total $ 34 $ - $ 36 $ - $ 37 $ 107
Projects 16 -20 & 18 -20
Sponsor Department:
Public Works Department
Biennial Real Estate Technical and Legal
Services
Category:
Miscellaneous
Funding for appraisals, environmental reports,
surveys, and lease preparation/review services for
Additional Annual
Prevailing Wage
City Real Estate activity.
O &M Costs:
None Project?
No
Project Number and Fiscal Year
16 -20
18 -20
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
C/C Tax
$ -
$ 18
$ -
$ 18
$ -
$ 36
Shoreline Community
-
8
-
9
-
17
Park Land
-
45
-
46
-
91
Total
$ -
$ 71
$ -
$ 73
$ -
$ 144
Page 7
Non - Discretionary Projects
All numbers are in thousands (1,000)
Project xx -21
Miscellaneous Water Main /Service Line
Replacement
Replace corroded and/or undersized water main
pipes on various streets. The replacements
include water services, fire hydrants and saddle
replacements.
Fundinu Sources
Water Fund
Total
Sponsor Department: Public Works Department
Category: Utilities
Additional Annual None Prevailing Wage yes
O &M Costs: Project?
Project Number and Fiscal Year
Sponsor Department:
15 -21
16 -21
17 -21
18 -21
19 -21
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
$ 2,165
$ 2,415
$ 2,465
$ 2,515
$ 2,565
$ 12,125
$ 2,165
$ 2,415
$ 2,465
$ 2,515 $ 2,565
$ 12,125
Project xx -22
Sponsor Department:
Public Works Department
TDA Project - Crosswalk Improvements at W.
Miscellaneous Storm /Sanitary Sewer Main
Category:
g n
Utilities
Replacement
Additional Annual
None Prevailing Wage Yes
intersection of Middlefield Road, Independence
O &M Costs:
Repair and replace storm and sanitary sewer
Additional Annual
None
Prevailing Wage
yes
pipes, manholes and systems identified by the
O &M Costs:
Various bike and pedestrian related projects.
Project?
City's annual line televising program.
17 -23 18 -23 19 -23
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19 Total
C/C Tax
Project Number and Fiscal Year
$ 10
$ 10 $ 10
15 -22 16 -22
17 -22
18 -22 19 -22
180
Funding Sources
2014 -15 2015 -16
2016 -17
2017 -18 2018 -19
Total
Wastewater Fund
$ 1,495
$ 1,525
$ 1,555
$ 1,585
$ 1,615
$ 7,775
Total
$ 1,495
$ 1,525
$ 1,555
$ 1,585
$ 1,615
$ 7,775
Project 15 -23
Sponsor Department:
Public Works Department
TDA Project - Crosswalk Improvements at W.
Category:
Traffic, Parking and Transportation
Middlefield /Independence /Thaddeus
Pedestrian safety improvements at the
Additional Annual
None Prevailing Wage Yes
intersection of Middlefield Road, Independence
O &M Costs:
Proj ect?
Avenue and Thaddeus Drive.
Projects 16 -23, 17 -23, 18 -23 & 19 -23
Various bike and pedestrian related projects.
Project Number and Fiscal Year
15 -23 16 -23
17 -23 18 -23 19 -23
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19 Total
C/C Tax
$ -
$ 10
$ 10 $ 10
$ 10
$ 40
Transportation Development Act (TDA) Funding
180
50
50
50
50
380
Total
$ 180
$ 60
$ 60
$ 60
$ 60
$ 420
Page 8
Non - Discretionary Projects
All numbers are in thousands (1,000)
Projects 15 -24, 17 -24 & 19 -24
Biennial ADA Improvements to City Facilities
Continuation of efforts to implement ADA
improvements at City facilities. Project is now
funded every other year.
Projects 16 -24 & 18 -24
Biennial Installation of ADA Curb Ramps
Install approximately 10 ADA - compliant curb
ramps throughout the City.
Sources
CIC Tax
Total
City Manager's Office/Public Works
Sponsor Department: Department
Category: Regulatory Requirements
Additional Annual None Prevailing Wage TBD/
O &M Costs: Project? Yes
Project Number and Fiscal Year
15 -24 16 -24 17 -24 18 -24 19 -24
2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
$ 86 $ 62 $ 90 $ 64 $ 93 $ 395
$ 86 $ 62 $ 90 $ 64 $ 93 $ 395
Project xx -25
Sponsor Department:
Public Works Department
Annual New Energy Conservation Measures
Category:
g n
Facilities
Fund energy conservation efforts in City
facilities.
Additional Annual
Prevailing Wage
O &M Costs:
None
Project?
TBD
Project Number and Fiscal Year
15 -25 16 -25
17 -25 18 -25 19 -25
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
CIC Tax
$ 172
$ 88
$ 179
$ 91
$ 187
$ 717
Total
$ 172 $ 88
$ 179 $ 91
$ 187
$ 717
Project xx -26 Sponsor Department: Community Services Department
Biennial Tennis Court Resurfacing
Periodic routine resurfacing of tennis courts at the Category: Parks and Recreation
following parks: Cuesta, Rengstorff, Cooper, g rY
Stevenson, Sylvan and Whisman. Additional Annual None Prevailing Wage Yes
O &M Costs: Project?
Project Number and Fiscal Year
15 -26 17 -26 19 -26
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
CIC Tax $ 80 $ - $ 84 $ - $ 87 $ 251
Total $ 80 $ - $ 84 $ - $ 87 $ 251
Page 9
Non - Discretionary Projects
All numbers are in thousands (1,000)
Projects 16 -26 & 18 -26 Sponsor Department: Public Works Department
Biennial PMP Recertification
Field inspection of all arterial and collector Category: Streets and Sidewalks
streets as required by the Metropolitan g n
Transportation Commission (MTC). Additional Annual Prevailing Wage
O &M Costs: None Project? No
Project Number and Fiscal Year
16 -26 18 -26
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
C/C Tax $ - $ 69 $ - $ 72 $ - $ 141
Total $ - $ 69 $ - $ 72 $ - $ 141
Projects 16 -27, 17 -27, 18 -27 & 19 -27
Sponsor Department:
Public Works Department
Traffic Signal Replacements (Location TBD)
Category:
Traffic, Parking and Transportation
Annual project to replace /upgrade one existing
traffic signal and controller that are at the end of
Additional Annual
None Prevailing Wage
Yes
their useful lives.
O &M Costs:
Project?
Project Number and Fiscal Year
16 -27
17 -27 18 -27 19 -27
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
C/C Tax
$
-
$ 379
$ 39
$ -
$ -
$ 418
Gas Tax
$
-
$ -
$ 348
$ -
$ -
$ 348
Vehicle Registration Fee (VRF) - Measure B Funding
$
-
$ -
$ -
$ 394
$ 402
$ 796
Total
1 $
-
$ 379
$ 387 $ 394
$ 402
$ 1,562
Page 10
Adopted FY 2014 -15 and Planned FY 2015 -16 through FY 2018 -19
Discretionary Projects
All numbers are in thousands (1,000)
Brief descriptions and funding sources for the projects below are provided on the pages indicated.
Proj.
No.
Discretionary Projects
Budget
Page
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
15 -27
Drew Avenue Reconstruction
$ 619
1
15 -28
Permanente Creek Trail, Rock Street to West Middlefield
Road, Design
370
1
15 -29
Interceptor and Central Trunk Main Rehabilitation,
Design
324
1
15 -30
Parking Technology Implementation
75
2
15 -31
Modifications to Grant /Phyllis /Martens Intersection
897
2
15 -32
Shoreline Boulevard Pathway (Villa Street to Wright
Avenue), Design
280
2
15 -33
City Bridge and Culvert Repairs
135
3
15 -34
Street Lighting Downtown, Assessment and Possible
Construction
150
3
15 -35
Citywide Trash Capture Feasibility Study
125
3
15 -36
Lower Stevens Creek Levee Improvements Study
275
4
15 -37
Permanente Creek Trail — Amphitheatre Parkway
Crossing, Construction
1,265
4
15 -38
Sailing Lake Access Road
225
4
15 -39
Shoreline Boulevard 101 Off -Ramp Modification
Feasibility Study
320
5
15 -40
Facilities Major Planned and Emergency Repairs
665
5
15 -41
1771 Rengstorff Avenue Park, Design
235
5
15 -42
Rengstorff Park Lighting Improvements
730
6
15 -43
Rengstorff Park Community Center, Design
2,900
6
15 -44
Mountain View Veterans Memorial
70
6
15 -45
Shoreline Golf Links Improvements
139
7
15 -46
City Hall Security
250
7
15 -47
East Whisman Precise Plan, EIR and Infrastructure Study
690
7
15 -48
Green Bike Lane Pilot Project
65
8
15 -49
Police Department/Library CCTV Replacement
267
8
Adopted FY 2014 -15 and Planned FY 2015 -16 through FY 2018 -19
Discretionary Projects
All numbers are in thousands (1,000)
Brief descriptions and funding sources for the projects below are provided on the pages indicated.
Proj.
No.
Discretionary Projects
Budget
Page
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
16 -28
Hackett Avenue Reconstruction
631
1
16 -29
Interceptor Force Trunk Main Rehabilitation,
Construction
3,900
8
16 -30
South Whisman Area Park, Design
835
9
16 -31
Shoreline Park Irrigation Replacement
1,026
9
16 -32
Fayette Area Park, Construction
1,650
9
16 -33
Police/Fire Administration Building Expansion, Design
2,000
10
16 -34
Regional Public Safety Communications System
150
10
16 -35
Miscellaneous Bike/Pedestrian Safety Project
300
10
16 -36
Permanente Creek Trail Extension - West Middlefield Rd
to McKelvey Park, Feasibility Study
55
11
16 -37
Graham Athletic Field Synthetic Turf Replacement
650
11
16 -38
Shoreline at Mountain View Master Plan
139
11
16 -39
771 Rengstorff Avenue Park, Construction
1,500
12
17 -28
Wagner Avenue Reconstruction
644
1
17 -29
South Whisman Area Park, Construction
4,670
9
17 -30
Facilities Major Planned and Emergency Repairs
190
5
17 -31
Police/Fire Radio Replacement
1,700
12
17 -32
Regional Public Safety Communications System
150
10
17 -33
Miscellaneous Bike/Pedestrian Safety Project
300
10
18 -28
Central Sewage Trunk Main Rehabilitation, Construction
3,600
12
18 -29
Rengstorff Park Community Center, Construction
17,100
13
18 -30
Regional Public Safety Communications System
150
10
19 -28
Regional Public Safety Communications System
150
10
Total: Discretionary Projects
$ 11,071
$ 12,836
$ 7,654
$ 20,850
$ 150
Discretionary Projects
All numbers are in thousands (1,000)
Project 15 -27, 16 -28 & 17 -28
Sponsor Department:
Public Works Department
Drew, Hackett, and Wagner Avenue
Category:
Streets and Sidewalks
Reconstruction Projects
Construction of curbs, gutters and driveway
Additional Annual
None Prevailing Wage
Yes
approaches and pavement on these Rex Manor
O &M Costs:
Project?
Neighborhood streets. Completion of these
projects will conclude a street improvement
strategy started in the Fiscal Year 2007 -08 CIP to
reconstruct 10 residential streets along Burgoyne
Street between San Ramon Avenue and Hackett
Avenue.
Project Number and Fiscal Year
15 -27 16 -28
17 -28
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
CIC Tax
$ 56
$ 57
$ 246
$ -
$ -
$ 359
124
178
-
-
-
302
Gas Tax
Vehicle Registration Fee (VRF) - Measure B Funding
439
396
398
-
-
1,233
Total
$ 619
$ 631
$ 644 $
Project 15 -28
Permanente Creek Trail, Rock Street to West
Middlefield Road, Design
Extension of the Permanente Creek Trail from its
terminus at Rock Street to West Middlefield
Road.
Sponsor Department: Public Works Department
Category: Parks and Recreation
Additional Annual None Prevailing Wage No
O &M Costs: Project?
Project Number and Fiscal Year
15 -28
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Shoreline Community $ 92 $ - $ - $ - $ - $ 92
Park Land 278 - - - - 278
Total 1 $ 370 $ - $ - $ - $ - $ 370
Project 15 -29
Interceptor and Central Trunk Main -
Rehabilitation, Design
Design of the Interceptor and Central Trunk Main
Rehabilitation construction projects planned for
FY 2015 -16 and FY 2017 -18, respectively.
Sponsor Department: Public Works Department
Category: Utilities
Additional Annual Prevailing Wage
O &M Costs: None Project? No
I Proiect Number and Fiscal Year I
15 -29
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Wastewater $ 324 $ - $ - $ - $ - $ 324
total $ 324 $ - $ - $ - $ - $ 324
Page 1
Discretionary Projects
All numbers are in thousands (1,000)
Project 15 -30 Sponsor Department: Community Development Department
Parking Technology Implementation Category: Traffic, Parking and Transportation
Funding for implementation of potential
wayfinding and parking guidance technology, and Additional Annual TBD Prevailing Wage No
an on -line payment platform. O &M Costs: Project?
Project Number and Fiscal Year
15 -30
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Parking District $ 75 $ - $ - $ - $ - $ 75
Total $ 75 $ - $ - $ - $ - $ 75
Project 15 -31
Modifications to Grant /Phyllis/Martens
Intersection
Pedestrian improvements including shortened
pedestrian crossing distances, elimination of free
right -turn lanes to reduce vehicle speeds, and
replacement of an aging traffic signal with a new
signal with a dedicated left -turn movement.
Sponsor Department: Public Works Department
Category: Traffic, Parking and Transportation
Additional Annual Prevailing Wage
O &M Costs: None Project? No
15 -31
ect Number and Fiscal Year
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 1 Total
Google Funding $ 300 $ - $ - $ - $ - $ 300
C/C Tax 597 - - - - 597
Total $ 897 $ - $ - $ - $ - $ 897
Project 15 -32
Shoreline Boulevard Pathway (Villa Street to
Wright Avenue), Design
Design of pathway and connection improvements
for bicycles and pedestrians along Shoreline
Boulevard between Villa Street and Wright
Avenue.
Funding Sources
C/C Tax
Prometheus Real Estate Group Fund
Total
Sponsor Department: Public Works Department
Category: Traffic, Parking and Transportation
Additional Annual None Prevailing Wage No
O &M Costs: Project?
Project Number and Fiscal Year
15 -32
2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
$ 180 $ - $ - $ - $ - $ 180
100 - - - - 100
$ 280 $ - $ - $ - $ - $ 280
Page 2
Discretionary Projects
All numbers are in thousands (1,000)
Project 15 -33
City Bridge and Culvert Repairs
Required minor repair work on City bridges as
identified in recently completed Caltrans and City
inspections.
Sponsor Department: Public Works Department
Category: Streets and Sidewalks
Additional Annual None Prevailing Wage Yes
O &M Costs: Project?
Project Number and Fiscal Year
15 -33
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
C/C Tax $ 135 $ - $ - $ - $ - $ 135
Total $ 135 $ - $ - $ - $ - $ 135
Project 15 -34
Street Lighting Downtown, Assessment and
Possible Construction
Assessment of lighting levels in the downtown
and possible installation of improvements.
Sponsor Department: Public Works Department
Category: Miscellaneous
Additional Annual Prevailing Wage
O &M Costs: None Project? No
Project Number and Fiscal Year
15 -34
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
C/C Tax $ 150 $ - $ - $ - $ - $ 150
Total $ 150 $ - $ - $ - $ - $ 150
Project 15 -35
Citywide Trash Capture Feasibility Study
Develop a plan to install trash capture devices on
the City's storm drain system to meet
requirements of the City's Regional Stormwater
Permit.
Sponsor Department: Public Works Department
Category: Regulatory Requirements
Additional Annual None Prevailing Wage No
O &M Costs: Project?
Project Number and Fiscal Year
15 -35
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Storm Drain Construction $ 125 $ - $ - $ - $ - $ 125
Total $ 125 $ - $ - $ - $ - $ 125
Page 3
Discretionary Projects
All numbers are in thousands (1,000)
Project 15 -36
Lower Stevens Creek Levee Improvements
Study
Alternatives analysis, geotechnical investigation,
and concept design for levee improvements to
protect from flooding and sea level rise.
Sponsor Department: Public Works Department
Category: Miscellaneous
Additional Annual None Prevailing Wage No
O &M Costs: Project?
I Proiect Number and Fiscal Year I
15 -36
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Shoreline Community $ 275 $ - $ - $ - $ - $ 275
Total $ 275 $ - $ - $ - $ - $ 275
Project 15 -37
Permanente Creek Trail — Amphitheatre
Parkway Crossing, Construction
Construct improvements to the existing Trail
under - crossing at Amphitheatre Parkway.
Sponsor Department: Public Works Department
Category: Parks and Recreation
Additional Annual Prevailing Wage
O &M Costs: 5,000 Project? Yes
Project Number and Fiscal Year
15 -37
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Shoreline Community $ 1,265 $ - $ - $ - $ - $ 1,265
Total $ 1,265 $ - $ - $ - $ - $ 1,265
Project 15 -38
Sailing Lake Access Road
Design, permit, and construct drainage and slope
stability improvements to the Access Road to
limit seepage and improve the levee's structural
capacity.
Sponsor Department: Public Works Department
Category: Miscellaneous
Additional Annual 3,000 Prevailing Wage Yes
O &M Costs: Project?
Project Number and Fiscal Year
15 -38
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Shoreline Community $ 225 $ - $ - $ - $ - $ 225
Total $ 225 $ - $ - $ - $ - $ 225
Page 4
Discretionary Projects
All numbers are in thousands (1,000)
Project 15 -39
Shoreline Boulevard 101 Off -Ramp
Modification Feasibility Study
Study alternative configurations of the Highway
101 off- and on -ramps at Shoreline Boulevard to
serve as a foundation for a subsequent Caltrans
Project Study Report.
Sponsor Department: Public Works Department
Category: Traffic, Parking and Transportation
Additional Annual None Prevailing Wage No
O &M Costs: Project?
I Proiect Number and Fiscal Year I
15 -39
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Shoreline Community $ 320 $ - $ - $ - $ - $ 320
Total $ 320 $ - $ - $ - $ - $ 320
Project 15 -40 & 17 -30
Sponsor Department:
Public Works Department
Facilities Major Planned and Emergency
Category:
g
Facilities
Repairs
Police /Fire Administration Building roof repair;
Additional Annual
None Prevailing Wage
TBD
replacement of City Hall conference room
O &M Costs:
Project?
furniture and carpeting; and technology upgrades
to building HVAC and lighting systems at City
Hall, Center for the Performing Arts, Library,
Senior Center, and Police /Fire Building.
Project Number and Fiscal Year
15 -40
17 -30
Funding Sources
2014 -15
2015 -16
2016 -17 2017 -18
2018 -19
Total
C/C Tax
$ 665
$ -
$ 190
$ -
$ -
$ 855
Total
$ 665
$ -
$ 190
$ -
$ - I
$ 855
Project 15 -41
771 Rengstorff Avenue Park, Design
Design of a new park at 771 North Rengstorff
Avenue. Design phase includes conducting
several public outreach meetings to determine the
scope for the park development at the property.
Sponsor Department: Public Works Department
Category: Parks and Recreation
Additional Annual Prevailing Wage
O &M Costs: None Project? No
I Proiect Number and Fiscal Year I
15 -41
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Park Land $ 235 $ - $ - S - $ - $ 235
Total $ 235 $ - $ - $ - $ - $ 235
Page 5
Discretionary Projects
All numbers are in thousands (1,000)
Project 15 -42
Rengstorff Park Lighting Improvements
Study of the Park's existing lighting system and
electrical service to determine if the existing
electrical service can support the additional
lights. Design and installation of additional lights
throughout the Park to increase lighting and
improve safety and security within the Park.
Replacement/ installation of new electrical wiring
to connect new lights to existing lighting system.
Possible grants of $299,000 (CDBG) and
$236,000 (State Housing Park Grant) would
reimburse the Park Land Dedication Fund.
Sponsor Department: Public Works Department
Category: Parks and Recreation
Additional Annual None Prevailing Wage yes
O &M Costs: Project?
I Proiect Number and Fiscal Year I
15 -42
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Park Land $ 730 $ - $ - $ - $ - $ 730
Total $ 730 $ - $ - $ - $ - $ 730
Project 15 -43 Sponsor Department: Public Works Department
Rengstorff Park Community Center, Design Category: Parks and Recreation
Design of the remodel and expansion of the g ry
existing Community Center. This includes an Additional Annual None Prevailing Wage No
investigation into the condition of the building's O &M Costs: Project?
structural, electrical, and mechanical systems,
and the development of architectural building
designs, and provisions for maintaining (possibly Project Number and Fiscal Year
limited) services during construction.
15 -43
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Park Land $ 2,900 $ - $ - $ - $ - $ 2,900
Total $ 2,900 $ - $ - $ - $ - $ 2,900
Project 15 -44
Sponsor Department:
Public Works Department
Mountain View Veterans Memorial
Category:
g rY
Miscellaneous
Construction of a new veterans memorial at Eagle
Park.
Additional Annual
Prevailing Wage
O &M Costs:
None
Project?
yes
Project Number and Fiscal Year
14 -44
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
C/C Tax
$ 60
$ -
$ - $ -
$ -
$ 60
Private Donations
$ 10
$ -
$ - $ -
$ -
$ 10
Total
$ 70
$ -
$ - $ -
$ -
$ 70
Page 6
Discretionary Projects
All numbers are in thousands (1,000)
Project 15 -45
Shoreline Golf Links Improvements
Refurbishment of fairway bunkers, replacement
of rotor sprinklers for the greens, turf
improvements, driving range upgrades, and new
golf course directional signage.
Sponsor Department: Community Services Department
Category: Parks and Recreation
Additional Annual None Prevailing Wage No
O &M Costs: Project?
I Proiect Number and Fiscal Year I
15 -45
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Shoreline Community $ 139 $ - $ - $ - $ - $ 139
Total $ 139 $ - $ - $ - $ - $ 139
Project 15 -46 Sponsor Department: Public Works Department
City Hall Security
City Hall security improvements to increase Category: Facilities
safety for the public and city staff. Additional Annual None Prevailing Wage No
O &M Costs: Project?
Project Number and Fiscal Year
15 -46
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
C/C Tax $ 250 $ - $ - $ - $ - $ 250
Total $ 250 $ - $ - $ - $ - $ 250
Project 15 -47
Sponsor Department:
Community Development Department
East Whisman Precise Plan, EIR and
Category:
g ry
Miscellaneous
Infrastructure Study
Creation of a new transit - oriented Precise Plan
Additional Annual
None Prevailing Wage
No
for the East Whisman area. The project also
O &M Costs:
Project?
includes technical assessments of existing public
facilities and utilities (water, sanitary sewer,
storm drainage, etc.) to determine their abilities to
serve the proposed new development and identify
what improvements will be required.
Project Number and Fiscal Year
15 -47
Funding Sources
2014 -15
2015 -16
2016 -17 2017 -18
2018 -19
Total
Water
$ 50
$ -
$ - $ -
$ -
$ 50
Wastewater
$ 50
$ -
$ - $ -
$ -
$ 50
Development Services
$ 590
$ -
$ - $ -
$ -
$ 590
Total
$ 690
$ -
$ - $ -
$ -
$ 690
Page 7
Discretionary Projects
All numbers are in thousands (1,000)
Project 15 -48
Green Bike Lane Pilot Project
Pilot project to improve bike safety through the
application of green paint to bike lanes in select
conflict areas to be determined.
Sponsor Department: Public Works Department
Category: Traffic, Parking and Transportation
Additional Annual Prevailing Wage
O &M Costs: TBD project? No
Proiect Number and Fiscal Year
15 -48
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Google Funding $ 65 $ - $ - $ - $ - $ 65
Total $ 65 $ - $ - $ - $ - $ 65
Project 15 -49
Police Department/Library CCTV
Replacement
Replace Police and Library closed circuit
television (CCTV) system hardware and
software. Expand camera coverage of Police/Fire
Administration Building exterior and Police
holding facility.
Sponsor Department: Police Department/Library
Category: Facilities
Additional Annual Prevailing Wage
O &M Costs: TBD Project? No
Proiect Number and Fiscal Year
15 -49
Funding Sources
2014 -15
2015 -16
2016 -17 2017 -18
2018 -19
Total
CIP Reserve
$ 130
$ -
$ - $ -
$ - $ -
$ -
$ 130
CIC Tax
$ 137
$ -
$ -
$ 137
Total
$ 267
$ -
$ - $ -
$ -
$ 267
Project 16 -29
Sponsor Department:
Public Works Department
Interceptor Force Trunk Main Rehabilitation,
Category:
g ry
Utilities
Construction
Rehabilitate 4,000 feet of the Interceptor Force
Additional Annual
None Prevailing Wage
yes
Trunk Main between the Sewage Pump Station
O &M Costs:
Project?
and the Palo Alto Interceptor Line.
Project Number and Fiscal Year
16 -29
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
Wastewater
$ -
$ 3,900
$ - $ -
$ -
$ 3,900
Total
$ -
$ 3,900
$ - $ -
$ -
$ 3,900
Page 8
Discretionary Projects
All numbers are in thousands (1,000)
Project 16 -30
Sponsor Department:
Public Works Department
Shoreline Park Irrigation Replacement
South Whisman Area Park, Design
Category:
g
Parks and Recreation
Replace irrigation systems at the North Shore and
Project 17 -29
Additional Annual
TBD Prevailing Wage
No
17 -29.
South Whisman Area Park, Construction
O &M Costs:
Project?
17-
Design and construction of a new park in the
Project Number and Fiscal Year
Project?
South Whisman Precise Plan Area.
16 -30
17 -29
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
Park Land
$ -
$ 835
$ 1,280
$ -
$ -
$ 2,115
Unidentified Funding
-
-
3,390
-
-
3,390
Total
$ - $ 835
$ 4,670 $ -
$ -
$ 5,505
Project 16 -31
Sponsor Department:
Community Services Department
Shoreline Park Irrigation Replacement
Category:
g rY
Utilities
Parks and Recreation
Replace irrigation systems at the North Shore and
Construction of an urban trail and park over the
Beach turf areas and install a new system for the
Additional Annual
None Prevailing Wage
No
Kite Lot turf.
O &M Costs:
Project?
Project?
Project Number and Fiscal Year
Project Number and Fiscal Year
16 -31
16 -32
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
Shoreline Community
$ -
$ 1,026
$ -
$ -
$ -
$ 1,026
Total
$ -
$ 1,026
$ -
$ -
$ -
1 $ 1,026
Project 16 -32
Sponsor Department:
Public Works Department
Fayette Area Park, Construction
Category:
g rY
Parks and Recreation
Construction of an urban trail and park over the
Hetch Hetchy right -of -way between El Camino
Additional Annual
$26,000 Prevailing Wage
Yes
Real West and Fayette Drive.
O &M Costs:
Project?
Project Number and Fiscal Year
16 -32
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
Park Land
$ -
$ 1,650
$ - $ -
$ -
$ 1,650
Total
$ -
$ 1,650
$ - $ -
$ -
$ 1,650
Page 9
Discretionary Projects
All numbers are in thousands (1,000)
Project 16 -33
Police /Fire Administration Building
Expansion, Design
Placeholder funding for design of the
expansion/renovation of the City's Police /Fire
Administration Building
Fundinu Sources
CIP Reserve
Total
Projects 16 -34, 17 -32, 18 -30 & 19 -28
Regional Public Safety Communications
System
Conversion of the City's Public Safety radio
infrastructure in support of the Silicon Valley
Regional Interoperability Authority's (SVRIA's)
Regional Communications System (RCS) project.
SVRIA's RCS project will provide Santa Clara
County public safety agencies with a common
police, fire, and emergency medical service radio
system that is compliant with Project 25
interoperability standards as established by the
Federal Communications Commission.
Sources
CIP Reserve
Total
Sponsor Department: Public Works Department
Category: Facilities
Additional Annual None Prevailing Wage No
O &M Costs: Project?
Project Number and Fiscal Year
16 -33
2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
$ - $ 2,000 $ - $ - $ - $ 2,000
$ - $ 2,000 $ - $ - $ -
Sponsor Department: Police Department
Category: Information Technology and
g Communications
Additional Annual Prevailing Wage
O &M Costs: TBD Project? No
Project Number and Fiscal Year
16 -34 17 -32 18 -30 19 -28
2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
$ - $ 150 $ 150 $ 150 $ 150 $ 600
$ - $ 150 $ 150 $ 150 $ 150 $ 600
Projects 16 -35 & 17 -33 Sponsor Department: Public Works Department
Miscellaneous Bike/Pedestrian Safety Project Category: Traffic, Parking and Transportation
Google funded pedestrian/bicycle safety projects
in select conflict areas to be determined. Additional Annual ,TBD Prevailing Wage TBD
O &M Costs: Project?
Project Number and Fiscal Year
16 -35 17 -33
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Google Funding $ - $ 300 $ 300 $ - $ - $ 600
Total $ - $ 300 $ 300 $ - $ - $ 600
Page 10
Discretionary Projects
All numbers are in thousands (1,000)
Project 16 -36
Permanente Creek Trail Extension - West
Middlefield Rd to McKelvey Park, Feasibility
Study
Feasibility study to extend the Permanente Creek
Trail from West Middlefield Road to McKelvey
Park.
Funding Sources
Shoreline Community
Park Land
Total
Project 16 -37
Graham Athletic Field Synthetic Turf
Replacement
Replace football /soccer field turf at Graham
Middle School reaching the end of its expected
10 -year life.
Funding Sources
School Site Maintenance Reserve
Total
Sponsor Department: Public Works Department
Category: Parks and Recreation
Additional Annual None Prevailing Wage No
O &M Costs: Project?
Project Number and Fiscal Year
16 -36
2014 -15
2015 -16
2016 -17 2017 -18
2018 -19
Total
$ -
$ 13
$ - $ -
$ - $ -
$ -
$ 13
$ -
$ 42
$ -
$ 42
$ -
$ 55
$ - $ -
$ -
$ 55
Sponsor Department: Public Works Department
Category: Parks and Recreation
Additional Annual None Prevailing Wage Yes
O &M Costs: Project?
Project Number and Fiscal Year
16 -37
2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
$ - $ 650 $ - $ - $ - $ 650
$ - $ 650 $ - $ - $ - $ 650
Project 16 -38 Sponsor Department: Community Services Department
Shoreline at Mountain View Master Plan Category: Parks and Recreation
Update existing Master Plan and recommend new g n
guidelines for traffic control, parking, way- Additional Annual None Prevailing Wage No
finding signage, trail signage, interpretive O &M Costs: Project?
signage, and improvements to the park entrance
at the gatehouse. Project Number and Fiscal Year
16 -38
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Shoreline Community $ - $ 139 $ - $ - $ - $ 139
Total $ - $ 139 $ - $ - $ - $ 139
Page 11
Discretionary Projects
All numbers are in thousands (1,000)
Project 16 -39 Sponsor Department: Public Works Department
771 Rengstorff Avenue Park, Construction Category: Parks and Recreation
Construction of a new City park at 771 North g
Rengstoff Avenue, which will include the Additional Annual $24,000 Prevailing Wage yes
planning and relocation of the Immigrant House. O &M Costs: Project?
Project Number and Fiscal Year
16 -39
Funding Sources 2014 -15 2015 -16 2016 -17 2017 -18 2018 -19 Total
Park Land $ - $ 1,500 $ - $ - $ - $ 1,500
Total $ - $ 1,500 $ - $ - $ - $ 1,500
Project 17 -31
Sponsor Department:
Police Department
Police /Fire Radio Replacement
Category:
g D
Information Technology and
Placeholder funding for the replacement of Police
Category:
Communications
and Fire Department radios in conjunction with
Additional Annual
None Prevailing Wage
yes
the City's support of SVRIA's RCS project (see
Additional Annual
Prevailing Wage
TBD
No
Project 16 -34, above). New RCS - compatible
O &M Costs:
Project?
radios are needed to enable communications
Project Number and Fiscal Year
regionally with other Santa Clara County
18 -28
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
Project Number and Fiscal Year
$ -
agencies.
$ -
$ 3,600
$ -
$ 3,600
Total
$ -
$ -
$ -
$ 3,600
17 -31
1 $ 3,600
Funding Sources
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
C/C Tax
$ -
$ -
$ 1,000
$ -
$ -
$ 1,000
Equipment Replacement
$ -
$ -
$ 700
$ -
$ -
$ 700
Total
$ -
$ -
$ 1,700
$ -
$ -
$ 1,700
Project 18 -28
Sponsor Department:
Public Works Department
Central Sewage Trunk Main Rehabilitation,
Category:
g D
Utilities
Construction
Rehabilitate 2,500 feet of the Central Sewage
Additional Annual
None Prevailing Wage
yes
Trunk Main between the Sewage Pump Station
O &M Costs:
Project?
and Highway 101.
Project Number and Fiscal Year
18 -28
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
Wastewater
$ -
$ -
$ -
$ 3,600
$ -
$ 3,600
Total
$ -
$ -
$ -
$ 3,600
$ -
1 $ 3,600
Page 12
Discretionary Projects
All numbers are in thousands (1,000)
Projects 18 -29
Sponsor Department:
Public Works Department
Rengstorff Park Community Center,
Category:
g
Parks and Recreation
Construction
Construction of the remodel and expansion of the
Additional Annual
TBD Prevailing Wage
YC
existing Community Center. This will include
O &M Costs:
Project?
building construction, site work, a traffic signal,
inspection, construction management, and other
construction- related costs.
Project Number and Fiscal Year
18 -29
Funding Sources
2014 -15 2015 -16
2016 -17 2017 -18 2018 -19
Total
Park Land
$ -
$ -
$ -
$ 10,811
$ -
$ 10,811
$ -
$ -
$ 5,000
$ -
$ 5,000
Strategic Property Acquisition Reserve
$ -
FY 2018 -19 Park Land Dedication Fund Allocation
$ -
$ -
$ -
$ 1,289
$ -
$ 1,289
Total
$ -
$ -
$ -
$ 17,100
$ -
$ 17,100
Page 13
Adopted Fiscal Year 2014 -15 Amendments to Existing Projects
All numbers are in thousands (1,000)
Brief descriptions and funding sources for the projects below are provided on the pages indicated.
Project No.
Amendments to Existing Projects
Budget
Page
08 -18
Information Technology Computer Projects
$ (97)
1
10 -18
Information Technology Computer Projects
$ (40)
1
12 -18
Information Technology Computer Projects
$ 75
2
14 -27
Tennis Court Resurfacing at Cooper, Stevenson, Sylvan, and Whisman
$ 79
2
13 -28
Dana Street Reconstruction
$ 149
3
13 -36
Fayette Area Park, Design
$ 360
3
10 -35
Create Zero Waste Action Plan
$ 15
4
14 -33
Interceptor Force Trunk Main - Manhole Construction, Inspection and Cleaning
$ 280
4
Total: Amendments to Existing Projects
$ 821
Amendments to Existing Projects
All numbers are in thousands (1,000)
Project 08 -18
Sponsor Department:
Information Technology
FY 2014 -15
Total Project
Funding
Information Technology Computer Projects
115
Information Technology and
115
For descriptions of the amendments to the various
Category:
Communications
125
information technology computer projects, please
105
33
33
-
-
see the information technology memorandum
Additional Annual
Prevailing Wage
None No
$ 431
included in this document.
O &M Costs:
Project?
FY2013 -14
Increased /(Decreased) FY2014 -15
Total Project
Funding Total Project
Funding Sources
Funding
for FY 2014 -15 Funding
CIP Reserve
85
$ -
$
85
218
(55)
163
CIC Tax
Water Fund
174
(12)
162
169
(10)
159
Wastewater Fund
Solid Waste Fund
30
(5)
25
Shoreline Community
31
(15)
16
Total
$ 707
$ (97)
$
610
Project 10 -18 Sponsor Department: Information Technology
Information Technology Computer Projects Information Technology and
For descriptions of the amendments to the various Category: Communications
information technology computer projects, please
Additional Annual Prevailing Wage
see the information technology memorandum None No
included in this document. O &M Costs: Project?
Funding Sources
FY 2013 -14
Total Project
Funding
Increased /(Decreased)
Funding
for FY 2014 -15
FY 2014 -15
Total Project
Funding
CIC Tax
Water Fund
Wastewater Fund
Solid Waste Fund
115
-
115
125
(20)
105
125
(20)
105
33
33
-
-
33
33
Shoreline Community
Total
$ 431
1 $ (40)
$ 391
Page 1
Amendments to Existing Projects
All numbers are in thousands (1,000)
Project 12 -18
Sponsor Department:
Information Technology
Information Technology Computer Projects
Information Technology and
For descriptions of the amendments to the various
Category:
Communications
information technology computer projects, please
see the information technology memorandum
Additional Annual
Prevailing Wage
None No
included in this document.
O &M Costs:
Project?
FY2013 -14
Increased /(Decreased) FY2014 -15
Total Project
Funding Total Project
Funding Sources
Funding
for FY 2014 -15 Funding
C/C Tax
436
$ 15
$
451
15
108
Water Fund
93
Wastewater Fund
84
15
99
Solid Waste Fund
29
15
44
Shoreline Community
94
-
94
Downtown Revitalization Authority
8
-
8
Building Services Fund
41
15
56
General Fund Reserve
15
-
15
Total
i $ 800
j $ 75
j $
875
Project 14 -27
Tennis Court Resurfacing at Cooper,
Stevenson, Sylvan, and Whisman
Additional funding for more extensive tennis
court resurfacing work and other improvements to
surrounding asphalt areas.
Sources
C/C Tax
Total
Sponsor Department: Community Services Department
Category: Parks and Recreation
Additional Annual None Prevailing Wage yes
O &M Costs: Project?
FY2013 -14 Increased /(Decreased) FY2014 -15
Total Project Funding Total Project
Funding for FY 2014 -15 Funding
$ 79 $ 79 $ 158
$ 79 $ 79 1 $ 158
Page 2
Amendments to Existing Projects
All numbers are in thousands (1,000)
Project 13 -28
Sponsor Department:
Public Works Department
Dana Street Reconstruction
Additional funding for the existing West Dana
Category:
Streets and Sidewalks
Street reconstruction project to provide a safe
pedestrian route to Mariposa Park from the
Additional Annual
Prevailing Wage
None Yes
adjacent neighborhood. Additional outside design
O &M Costs:
Project?
services are required.
FY2013 -14
Increased /(Decreased) FY2014 -15
Total Project
Funding Total Project
Funding Sources
Funding
for FY 2014 -15 Funding
C/C Tax
$ 20
$ 149
$ 169
Gas Tax
$ 205
$ -
205
Total
$ 225
$ 149
1 $ 374
Project 13 -36
Fayette Area Park, Design
Additional funding to complete design of an
urban trail and park over the Hetch Hetchy right -
of -way between El Camino Real West and
Fayette Drive. The existing project only funds the
conceptual design of the trail /park. The additional
funding will allow for the preparation of full
construction documents.
Sources
Park Land
Total
Sponsor Department: Public Works Department
Category: Parks and Recreation
Additional Annual Prevailing Wage
O &M Costs: None Project? No
FY2013 -14 Increased /(Decreased) FY2014 -15
Total Project Funding Total Project
Funding for FY 2014 -15 Funding
$ 200 $ 360 $ 560
$ 200 $ 360 1 $ 560
Page 3
Amendments to Existing Projects
All numbers are in thousands (1,000)
Project 10 -35
Create Zero Waste Action Plan
Additional funding is needed to complete a waste
characterization study and prepare a zero waste
plan to achieve a 90 percent diversion rate by
2021.
Waste
total
Fundinu Sources
Sponsor Department: Public Works Department
Category: Regulatory Requirements
Additional Annual None Prevailing Wage No
O &M Costs: Project?
FY2013 -14 Increased /(Decreased) FY2014 -15
Total Project Funding Total Project
Funding for FY 2014 -15 Funding
230 $ 15 $ 245
$ 230 $ 15 $ 245
Project 14 -33
Sponsor Department:
Public Works Department
Interceptor Force Trunk Main - Manhole
Category:
g
Utilities
Construction, Inspection and Cleaning
A preliminary study and geotechnical
Additional Annual
None Prevailing Wage Yes
investigation has found the site condition to be
O &M Costs:
Project?
much more complex related to soil conditions,
groundwater levels, and depth of the trunk
main. Additional funding is needed to install 4
manholes, then inspect and clean 4,000 feet of the
Interceptor Force Trunk Main between the
Sewage Pump Station and the Palo Alto
FY 2013 -14
Increased /(Decreased)
FY 2014 -15
Interceptor Line.
Total Project
Funding
Total Project
Funding Sources
Funding
for FY 2014 -15
Funding
Wastewater
$ 250
$ 280
$ 530
Total
$ 250
$ 280
$ 530
Page 4
Cash Flow Analysis of Major Funding Sources
All numbers are in thousands (1,000)
CIP Reserve
Estimated Available Funding as of July 1
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
$ 2,810
incl'd above
21
$
2,701
-
-
$
551
-
-
$ 401
- J
-
$
251
-
Net Revenue Available for Fiscal Year
Balance from Projects to be Closed on June 30, 2012
$
-
Amount Available for Capital Projects
Capital Improvement Projects
$
2,831
-
130
-
$
$
2,701
-
2,150
-
$
$
551 $ 401
- $ -
150 150
- -
$
251
Non-Discretionary
Discretionary
$
-
150
Amendments to Existing Projects
1,280
9,211
-
Total of All Projects
Estimated Available Balance at June 30
$
$
130
2,701
$
$
2,150
551
$
$
150
401
$ 150
$ 251
$
$
150
101
Construction Tax - Real Property Conveyance Tax Fund
Park Land Dedication Fund
Estimated Available Funding as of July 1
2014
-15
2015
-16
2016
-17
2017
-18
2018
-19
Estimated Available Funding as of July 1
$
8,559
$
3,608
$
2,889
$
283
$
442
Net Revenue Available for Fiscal Year
incl'd
above
-
-
2,214
$
$
1,918
$ 4,072
$ 8,791
2,766
1,280
9,211
2,840
Balance from Projects to be Closed on June 30, 2012
$ -
633
-
-
-
-
Amount Available for Capital Projects
$
9,192
$
5,822
$
4,807
$
3,049
$
3,282
Capital Improvement Projects
$
2,876
$
3,088
$
2,607J
Non- Discretionary
$ 3,166
$
3,173
Discretionary
2,230
57
1,436
-
188
Amendments to Existing Projects
-
-
-
-
Total of All Projects
$
5,584
$
2,933
$
4,524
$
2,607
$
3,173
Estimated Available Balance at June 30
$
3,608
$
2,889
$
283
$
442
$
109
Park Land Dedication Fund
Estimated Available Funding as of July 1
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
$ 15,621
incl'd above
-
$ 11,118
1,745
-
$
8,791
1,700
-
$
9,211
1,646 J
-
$ -
1,289
-
Net Revenue Available for Fiscal Year
Balance from Projects to be Closed on June 30, 2012
Amount Available for Capital Projects
Capital Improvement Projects
Non- Discretionary
$
$
15,621
-
4,143
360
$ 12,863
$ 45
4,027
-
$
$
10,491
-
1,280
-
$
$
10,857
46J
10,811
-
$ 1,289
$ -
Discretionary
Amendments to Existing Projects
-
-
Total of All Projects
Estimated Available Balance at June 30
$
$
4,503
11,118
$ 4,072
$ 8,791
$
$
1,280
9,211
$
$
10,857
$ -
Page l
5 -Year
Total
2,730
$ 2,730
5 -Year
Total
$ 14,910
3,723
188
$ 18,821
5 -Year
Total
$ 91
20,261
360
$ 20,712
Cash Flow Analysis of Major Funding Sources
All numbers are in thousands (1,000)
Gas Tax Fund
Estimated Available Funding as of July 1
2014 -15
2015 -16
2016 -17
2017 -18
1 2018 -19
$ 1,701
incl'd above
$
977
678
-
$
739
679
-
$ 317
68
-
$
235
682
Net Revenue Available for Fiscal Year
Balance from Projects to be Closed on June 30, 2012
124
$
-
Amount Available for Capital Projects
Capital Improvement Projects
$
1,825
$
1,655
$
1,418
$ 1,003
$
917
Non - Discretionary
Discretionary
$
724
124
$
738
178
-
$
1,101
-
-
$ 768
-
-
$
783
-
Amendments to Existing Projects
-
413
-
Total of All Projects
Estimated Available Balance at June 30
$
$
848
977
$
$
916
739
$
$
1,101
317
$ 768
$ 235
$
$
783
134
Vehicle Registration Fee (VRF) - Measure B Funding
Shoreline Regional Park Community Fund
Estimated Available Funding as of July 1
2014
-15
2015
-16
2016
-17
2017
-18
2018
-19
Estimated Available Funding as of July 1
$
440 $
1
$
5
$
7
$
13
Net Revenue Available for Fiscal Year
incl'd
above
-
400
-
701
400
-
400
-
Total of All Projects
Estimated Available Balance at June 30
400
-
Balance from Projects to be Closed on June 30, 2012
Amount Available for Capital Projects
$
440 $
401
$
405
$
407
$
413
Capital Improvement Projects
$
- $
-
$
-
i
$
394
Non- Discretionary
$
402
Discretionary
439
396
398
-
-
Amendments to Existing Projects
-
-
-
-
-
Total of All Projects
$
439
$
396
$
398
$
394
$
402
Estimated Available Balance at June 30
$
1
$
5
$
7
$
13
$
11
Shoreline Regional Park Community Fund
Estimated Available Funding as of July 1
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
$ 2,209
incl'd above
802
$
-
2,300
-
$
455
2,300
-
$ 2,080
2,300
-
$
3,682
2,300
-
Net Revenue Available for Fiscal Year
Balance from Projects to be Closed on June 30, 2012
Amount Available for Capital Projects
Capital Improvement Projects
Non- Discretionary
$
$
3,011 $
710 $
2,316
15
2,300
667
1,178
-
$
$
2,755
675
-
-
$ 4,380
$ 698
-
-
$
5,982
$
701
Discretionary
Amendments to Existing Projects
-
-
Total of All Projects
Estimated Available Balance at June 30
$
$
3,011 $
- $
1,845
455
$
$
675
2,080
$ 698
$ 3,682
$
$
701
5,281
Page 2
5 -Year
Total
$ 4,114
302
$ 4,416
5 -Year
Total
$ 796
1,233
$ 2,029
5 -Year
Total
$ 3,451
3,494
(15
$ 6,930
Cash Flow Analysis of Major Funding Sources
All numbers are in thousands (1,000)
Storm Drain Construction Fund
Estimated Available Funding as of July 1
Net Revenue Available for Fiscal Year
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
$ 626
incl'd above
$
496
21
-
$
488
23
-
$ 481
26
-
$
477
31
-
Balance from Projects to be Closed on June 30, 2012
24
Amount Available for Capital Projects
Capital Improvement Projects
$
650
$
517
$
511
$ 507
$
508
Non - Discretionary
Discretionary
$
29
125
$
29
-
$
30
-
$ 30
$
31
-
Amendments to Existing Projects
$
-
Capital Improvement Projects
-
Balance from Projects to be Closed on June 30, 2012
-
-
$
-
Total of All Projects
Estimated Available Balance at June 30
$
$
154
496
$
$
29
488
$
$
30
481
$ 30
$ 477
$
$
31
477
Water Fund
Wastewater Fund
2014
-15
2015
-16
2016
-17
2017
-18
2018
-19
Estimated Available Funding as of July 1
$
3,892
$
1,012
$
507
$
241
$
152
Net Revenue Available for Fiscal Year
incl'd
above
2,524
-
2,826
3,065
Amount Available for Capital Projects
3,065
5,290
-
4,543
-
$
-
Capital Improvement Projects
-
Balance from Projects to be Closed on June 30, 2012
1
Amount Available for Capital Projects
$
3,893
$
3,536
$
3,333
$
3,306
$
3,217
Capital Improvement Projects
Discretionary
-
Amendments to Existing Projects
265
-
- -
Non - Discretionary
$
2,848
$
3,029
$
3,092
$
3,154
$
3,217
Discretionary
$
50
$ (1,166) $ (4,835)
-
(4,905)
-
-
-
Amendments to Existing Projects
(17)I
-
-
-
-
Total of All Projects
$
2,881
$
3,029
$
3,092
$
3,154
$
3,217
Estimated Available Balance at June 30
$
1,012
$
507
$
241
$
152
$
-
Wastewater Fund
Page 3
5 -Year
Total
$ 149
125
$ 274
5 -Year
Total
$ 15,340
50
(17
$ 15,373
5 -Year
Total
$ 8,975
7,874
265
$ 17,114
2014
-15
2015
-16
2016 -17 2017 -18
2018
-19
Estimated Available Funding as of July 1
$
incl'd
5,285
above
$
2,873
$ (1,104)
$ (1,166)
$
(4,835)
Net Revenue Available for Fiscal Year
1,670 1,720
1,747
1,782
Balance from Projects to be Closed on June 30, 2012
5
-
-
-
-
Amount Available for Capital Projects
$
5,290
$
4,543
$ 616 $ 581
$
(3,053)
Capital Improvement Projects
Non - Discretionary
$
1,778
374
$
1,747
3,900
$ 1,782 $ 1,816
- 3,600
$
1,852
Discretionary
-
Amendments to Existing Projects
265
-
- -
-
Total of All Projects
$
2,417
$
5,647
$ 1,782 $ 5,416
$
1,852
Estimated Available Balance at June 30
$
2,873
$
(1,104)
$ (1,166) $ (4,835)
$
(4,905)
Page 3
5 -Year
Total
$ 149
125
$ 274
5 -Year
Total
$ 15,340
50
(17
$ 15,373
5 -Year
Total
$ 8,975
7,874
265
$ 17,114
Cash Flow Analysis of Major Funding Sources
All numbers are in thousands (1,000)
Solid Waste Fund
Estimated Available Funding as of July 1
2014 -15 2015 -16
2016 -17
2017 -18
2018 -19
$ 270 $
incl'd above
84
59
272
-
$
38
285
-
$
25
292
-
$
12
299
Net Revenue Available for Fiscal Year
Balance from Projects to be Closed on June 30, 2012
-J
-
Amount Available for Capital Projects
Capital Improvement Projects
$
354
$
331
$
323
$
317
$
311
Non - Discretionary
Discretionary
$
270
-
$
293
-
-
$
298
-
-
$
305J
�
-
$
311
$
-
Amendments to Existing Projects
25
$ -
-
Total of All Projects
Estimated Available Balance at June 30
$
$
295
59
$
$
293
38
$
$
298
25
$
$
305
12
$
$
311
-
Equipment Maintenance and Replacement Fund
Development Services Fund
2014
-15
2015 -16
2016
-17
2017
-18 2018 -19
Estimated Available Funding as of July 1
$
784
$ 700
$
700
$
-J
$
Net Revenue Available for Fiscal Year
incl'd
above
-
-
-
$
618 $ -
-
Balance from Projects to be Closed on June 30, 2012
$ -
-
-
-
-
Amount Available for Capital Projects
$
784
$ 700
$
700
$
-
$ -
Capital Improvement Projects
-
-
-
Total of All Projects
$
618 $ -
$ -
$ -
Non- Discretionary
$
84
$ -
$
-
$
-
$ -
Discretionary
-
-
700
-
Amendments to Existing Projects
-
-
-
-
Total of All Projects
$
84
$ -
$
700
$
-
$ -
Estimated Available Balance at June 30
$
700
$ 700
$
-
$
-
$ -
Development Services Fund
Page 4
5 -Year
Total
$ 1,477
25
$ 1,502
5 -Year
Total
$ 84
700
$ 784
5 -Year
Total
$ 13
590
15
$ 618
2014
-15
2015 -16
2016 -17
2017 -18
2018 -19
Estimated Available Funding as of July 1
$
incl'd
618
above
$ -
-
$ -
-
$
-
$
-
Net Revenue Available for Fiscal Year
Balance from Projects to be Closed on June 30, 2012
-
-
-
-
-
Amount Available for Capital Projects
$
618 $ -
$ -
$ -
$ -
Capital Improvement Projects
Non- Discretionary
$
13 $ -
590 -
$ -
-
-
$ -
Discretionary
-
Amendments to Existing Projects
15 -
-
-
-
Total of All Projects
$
618 $ -
$ -
$ -
$ -
Estimated Available Balance at June 30
$
- $ -
$ -
$
Page 4
5 -Year
Total
$ 1,477
25
$ 1,502
5 -Year
Total
$ 84
700
$ 784
5 -Year
Total
$ 13
590
15
$ 618
Cash Flow Analysis of Major Funding Sources
All numbers are in thousands (1,000)
Strategic Property Acquisition Reserve
Estimated Available Funding as of July 1
Net Revenue Available for Fiscal Year
2014 -15
2015 -16 2016 -17
2017 -18
2018 -19
$ 5,000
incl'd above
-
$ 5,000 $ 5,000
- -
$ 5,000
$
-
Balance from Projects to be Closed on June 30, 2012
- -
-
-
Amount Available for Capital Projects
Capital Improvement Projects
$ 5,000
$ -
-
-
$ 5,000 $ 5,000
$ 5,000
$ -
Non- Discretionary
Discretionary
$ -
- 1
$ -
-
$ -
$ -
5,000
-
Amendments to Existing Projects
-
-
-
-
Total of All Projects
Estimated Available Balance at June 30
$ -
$ 5,000
$ - $ -
$ 5,000 $ 5,000
$ 5,000
$ -
$ -
$ -
Page 5
5 -Year
Total
5,000
$ 5,000
Projects by Category
All numbers are in thousands (1,000)
Streets and Sidewalks
ro' No
Project
2014 -15 2015 -16
2016 -17
2017 -18
2018 -19
Total
Non - Discretionary
xx -01
Street Resurfacing Program
$ 861
$ 879
$ 897
$ 914
$ 932
$ 4,483
xx -03
Slurry Seal Program
126
129
131
134
137
657
xx -06
Concrete Sidewalk/Curb Repairs
287
293
299
305
311
1,495
xx -12
Street Lane Line and Legend Repainting
416
54
363
56
378
1,267
xx -26
Biennial PMP Recertification
L -
69
-
1 72
1 -
i 141
Sub - total: Non-Discretionary
$ 1,690
$ 1,424
$ 1,690
$ 1,481
$ 1,758
$ 8,043
Discretionary
15 -27
Drew Avenue Reconstruction
619
-
-
-
-
-
619
135
15 -33
City Bridge and Culvert Repairs
135
-
-
-
16 -28
Hackett Avenue Reconstruction
-
631
-
-
-
631
17 -28
Wagner Avenue Reconstruction
-
-
644
-
-
644
Sub - total: Discretionary
$ 754
$ 631
$ 644
$ -
$ -
$ 2,029
New
Prior
Amended
Total
Funding
Project
Project
New
roj No
Amendments to Existing Projects
Funding
Funding
Funding
13 -28
Dana Street Reconstruction
1 149
1
1 225
374
149
Sub - total: Amendments to Existin Projects
$ 149
$ 149
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Total: Streets and Sidewalks
$ 2,593
$ 2,055
$ 2,334
$ 1,481
$ 1,758
$ 10,221
Page 1
Projects by Category
All numbers are in thousands (1,000)
Page 2
Utilities
ro' No
Project
2014 -15 2015 -16
2016 -17
2017 -18
2018 -19
Total
Non - Discretionary
xx -04
Water System Improvements
$ 533
$ 544
$ 555
$ 566
$ 577
$ 2,775
xx -05
Wastewater System Improvements
149
152
155
158
162
776
xx -17
Shoreline Infrastructure Maintenance
230
234
239
244
249
1,196
xx -21
Miscellaneous Water Main/Service Line
Replacement
2,165
2,415
2,465
2,515
2,565
12,125
xx -22
Miscellaneous Storm/Sanitary Sewer Main
Replacement
1,495
1,525
1,555
1,585
1,615
7,775
Sub - total: Non-Discretionary
$ 4,572
$ 4,870
$ 4,969
$ 5,068
$ 5,168
$ 24,647
Discretionary
15 -29
Interceptor and Central Trunk Main Rehabilitation,
Design
324
-
-
-
-
324
16 -29
Interceptor Force Trunk Main Rehabilitation,
Construction
-
3,900
-
-
-
3,900
16 -31
Shoreline Park Irrigation Replacement
-
1,026
-
-
-
1,026
18 -28
Central Sewage Trunk Main Rehabilitation,
Construction
-
-
-
3,600
-
3,600
Sub - total: Discretionary
$ 324
$ 4,926
$ -
$ 3,600
$ -
$ 8,850
New
Prior
Amended
Total
Funding
Project
Project
New
roj No
Amendments to Existing Projects
Funding
Funding
Funding
14 -33
Interceptor Force Trunk Main - Manhole
Construction, Inspection and Cleaning
1 250
530
280
Sub - total: Amendments to Existing Projects
$ 280
$ 280
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Total: Utilities
$ 5,176
$ 9,796
$ 4,969
$ 8,668
$ 5,168
$ 33,777
Page 2
Projects by Category
All numbers are in thousands (1,000)
Traffic, Parking and Transportation
ro' No
Project
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Non - Discretionary
xx -02
Traffic and Streetlight Improvements
$ 302
$ 322
$ 341 $ 349
131 134
$ 356
137
$ 1,670
657
xx -15
Annual Traffic Studies/NTMP Improvements
126
129
15 -23
TDA Projects - Crosswalk Improvements at W.
Middlefield /Independence /Thaddeus
180
-
-
-
-
180
xx -23
TDA Projects
-
60
60
60
60
240
xx -27
Traffic Signal Replacements (Location TBD)
-
379
387
394
402
1,562
Sub - total: Non-Discretionary
$ 608
$ 890
$ 919
$ 937
$ 955
$ 4,309
Discretionary
15 -30
Parking Technology Implementation
75
-
-
-
-
75
15 -31
Modifications to Grant/Phyllis/Martens Intersection
897
-
-
-
-
897
15 -32
Shoreline Boulevard Pathway (Villa Street to
Wright Avenue), Design
280
-
-
-
-
280
15 -39
Shoreline Boulevard 101 Off -Ramp Modification
Feasibility Study
320
-
-
-
-
320
15 -48
Green Bike Lane Pilot Project
65
-
-
-
-
65
16 -35
Miscellaneous Bike/Pedestrian Safety Project
-
300
-
-
-
300
17 -33
Miscellaneous Bike/Pedestrian Safety Project
-
-
300
-
-
300
Sub - total: Discretionary
$ 1,637
$ 300
$ 300
$ -
$ -
$ 2,237
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Total: Traffic, Parking & Transportation
$ 2,245
$ 1,190
$ 1,219
$ 937
$ 955
$ 6,546
Page 3
Projects by Category
All numbers are in thousands (1,000)
Parks and Recreation
ro' No
Project
2014 -15 2015 -16
2016 -17
2017 -18
2018 -19
Total
Non - Discretionary
xx -07
Parks Pathway Resurfacing
$ 78
$ 79
$ 81
$ 82
84
$ 404
xx -08
Shoreline Pathway, Roadway, Parking
Improvements
184
187
191
195
199
956
xx -09
Forestry Maintenance Program and Street Tree
Replanting
299
305
311
317
323
1,555
xx -19
Biennial Park Renovations /Improvements
103
-
108
-
112
323
xx -19
Biennial Median Renovations and Roadway
Landscape Renovations
70
73
-
143
xx -20
Biennial Good Neighbor Fence Replacements
34
-
36
-
37
107
xx -26
Biennial Tennis Court Resurfacing
80
-
84
-
87
251
Sub - total: Non-Discretionary
$ 778
$ 641
$ 811
$ 667
$ 842
$ 3,739
Discretionary
15 -28
Permanente Creek Trail, Rock Street to West
Middlefield Road, Design
370
-
-
-
-
370
15 -37
Permanente Creek Trail — Amphitheatre Parkway
Crossing, Construction
1,265
-
-
-
-
1,265
15 -41
771 Rengstorff Avenue Park, Design
235
-
-
-
-
235
15 -42
Rengstorff Park Lighting Improvements
730
-
-
-
-
730
15 -43
Rengstorff Park Community Center, Design
2,900
-
-
-
-
2,900
15 -45
Shoreline Golf Links Improvements
139
-
-
-
-
139
16 -30
South Whisman Area Park, Design
-
835
-
-
-
835
16 -32
Fayette Area Park, Construction
-
1,650
-
-
-
1,650
16 -36
Permanente Creek Trail Extension - West
Middlefield Rd to McKelvey Park, Feasibility
Study
-
55
-
-
-
55
16 -37
Graham Athletic Field Synthetic Turf Replacement
-
650
-
-
-
650
16 -38
Shoreline at Mountain View Master Plan
-
139
-
-
-
139
16 -39
771 Rengstorff Avenue Park, Construction
-
1,500
-
-
-
1,500
17 -29
South Whisman Area Park, Construction
-
-
4,670
-
-
4,670
18 -29
Rengstorff Park Community Center, Construction
-
-
-
17,100
-
17,100
Sub - total: Discretionary
$ 5,639
$ 4,829
$ 4,670
$ 17,100
$ -
$ 32,238
New
Prior
Amended
Total
Funding
Project
Project
New
roj No
Amendments to Existing Projects
Funding
Funding
Funding
14 -27
Tennis Court Resurfacing at Cooper, Stevenson,
Sylvan, and Whisman
79
79
158
79
13 -36
Fayette Area Park, Design
360
200
1 560
360
Sub - total: Amendments to Existing Pro'ects
$ 439
$ 439
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Total: Parks and Recreation
$ 6,856
$ 5,470
$ 5,481
$ 17,767
$ 842
$ 36,416
Page 4
Projects by Category
All numbers are in thousands (1,000)
Facilities
ro' No
Project
2014 -15 2015 -16
2016 -17
2017 -18
2018 -19
Total
Non - Discretionary
Non - Discretionary
xx -18
xx -14
Facilities Maintenance Plan
$ 517
$ 527
$ 538
$ 549
559
$ 2,690
xx -16
Maintenance Agreement for JPB /VTA Transit
57
59
60
61
62
299
xx -25
Annual New Energy Conservation Measures
172
88
179
91
187
717
Regional Public Safety Communications System
Sub - total: Non-Discretionary
$ 746
$ 674
$ 777
$ 701
$ 808
$ 3,706
Police /Fire Radio Replacement
Discretionary
-
1,700
-
-
1,700
17 -32
15 -40
Facilities Major Planned and Emergency Repairs
665
-
-
-
-
665
15 -46
City Hall Security
250
-
-
-
-
250
15 -49
Police Department/Library CCTV Replacement
267
-
-
-
-
267
16 -33
Police/Fire Administration Building Expansion,
Design
-
2,000
-
-
-
2,000
17 -30
Facilities Major Planned and Emergency Repairs
-
-
190
-
-
190
Sub - total: Discretionary
$ 1,182
$ 2,000
$ 190
$ -
$ -
$ 3,372
Funding
Project
Project
New
roj No
Amendments to Existing Projects
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Information Technology Computer Projects
Total: Facilities
$ 1,928 $ 2,674 $ 967
$ 701
$ 808
$ 7,078
Information Technology and Communications
Pro' No
Project
2014 -15
2015 -16 1 2016 -17 2017 -18
2018 -19
Total
Non - Discretionary
xx -18
Information Technology Computer Projects
$ 1,011
$ 527
$ 538
$ 550
560
$ 3,186
Sub - total: Non-Discretionary
$ 1,011
$ 527
$ 538
$ 550
$ 560
$ 3,186
Discretionary
16 -34
Regional Public Safety Communications System
-
150
-
-
-
150
17 -31
Police /Fire Radio Replacement
-
-
1,700
-
-
1,700
17 -32
Regional Public Safety Communications System
-
-
150
-
-
150
18 -30
Regional Public Safety Communications System
-
-
-
150
-
150
19 -28
Regional Public Safety Communications System
-
-
i -
i -
I 150
150
Sub - total: Discretionary
$ -
$ 150
$ 1,850
$ 150
$ 150
$ 2,300
New
Prior
Amended
Total
Funding
Project
Project
New
roj No
Amendments to Existing Projects
Funding
Funding
Funding
08 -18
Information Technology Computer Projects
(97)
707
610
(97)
10 -18
Information Technology Computer Projects
(40)
431
391
(40)
12 -18
Information Technology Computer Projects
75
1
800
1 875
75
Sub - total: Amendments to Existing Projects
$ (62
$ (62)
2014 -15
2015 -16 2016 -17 2017 -18
2018 -19
Total
Total: Information Technology and
Communications
$ 949
$ 677 $ 2,388 $ 700
$ 710
$ 5,424
Page 5
Projects by Category
All numbers are in thousands (1,000)
Regulatory Requirements
roj No
roj No
Project
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Non - Discretionary
Non - Discretionary
$ 17,830
$ 30,779
$ 10,732
1 $103,461
xx -11
xx -10
Shoreline Landfill Cap Maintenance and Repairs
$ 126
$ 129
$ 131
$ 134
137
$ 657
xx -13
Landfill Gas /Leachate System Repairs &
Improvements
126
129
131
134
137
657
xx -24
Biennial ADA Improvements to City Facilities
86
$ 124
90
93
269
xx -24
Biennial Installation of ADA Curb Ramps
62
64
Street Lighting Downtown, Assessment and
Possible Construction
126
-
Sub - total: Non-Discretionary
$ 338
$ 320
$ 352
$ 332
$ 367
$ 1,709
-
Discretionary
-
-
275
15 -38
Sailing Lake Access Road
225
15 -35
Citywide Trash Capture Feasibility Study
125
-
-
-
-
125
-
Sub - total: Discretionary
$ 125
$ -
$ -
$ -
$ -
$ 125
-
-
-
-
690
Sub- total: Discretionary
$ 1,410
$ -
$ -
New
$ -
Prior
Amended
Total
Funding
Project
Project
New
roj No
Amendments to Existing Projects
2018 -19
Total
Funding
Funding
$ 1,526
Funding
10 -35
Create Zero Waste Action Plan
1 15
1
230
245
15
Sub - total: Amendments to Existin Projects
$ 15
$ 15
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Total: Regulatory Requirements
$ 478
$ 320
$ 352
$ 332
$ 367
$ 1,849
Miscellaneous
roj No
Project
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Grand Total: All Categories
Non - Discretionary
$ 22,369
$ 17,830
$ 30,779
$ 10,732
1 $103,461
xx -11
Developer Reimbursements
$ 116
$ 116
$ 120
$ 120
$ 124
-
$ 596
144
xx -20
Biennial Real Estate Technical and Legal Services
-
71
-
73
Sub - total: Non-Discretionary
$ 116
$ 187
$ 120
$ 193
$ 124
$ 740
Discretion ary
15 -34
Street Lighting Downtown, Assessment and
Possible Construction
150
-
-
-
-
$ 150
15 -36
Lower Stevens Creek Levee Improvements Study
275
-
-
-
-
275
15 -38
Sailing Lake Access Road
225
-
-
-
-
225
15 -44
Mountain View Veterans Memorial
70
-
-
-
-
70
15 -47
East Whisman Precise Plan, EIR and Infrastructure
Study
690
-
-
-
-
690
Sub- total: Discretionary
$ 1,410
$ -
$ -
$ -
$ -
$ 1,410
2014 -15
2015 -16 2016 -17
2017 -18
2018 -19
Total
Total: Miscellaneous
$ 1,526
$ 187 $ 120
$ 193
$ 124
$ 2,150
Page 6
2014 -15
2015 -16
2016 -17
2017 -18
2018 -19
Total
Grand Total: All Categories
$ 21,751
$ 22,369
$ 17,830
$ 30,779
$ 10,732
1 $103,461
Page 6
Unscheduled Projects
Projects moving from the Unscheduled Projects List to the Five -Year CIP will require updated cost estimates.
Item Project Description Estimated Cost
US -1 San Antonio Road Improvement Project
Construction of dedicated bicycle lanes on San Antonio Road from El
Camino Real to California Street.
US -2 Rehabilitation of the Cuesta Park Tennis Facility
Rehabilitation of the Cuesta Park Tennis Facility to improve
functionality and accessibility.
US -3 Mountain View Center for the Performing Arts SecondStage
Addition, Construction
Construction of an 1,800 square foot addition to allow concurrent use
of the Main Stage and Second Stage and increase the marketability and
use of the Center for the Performing Arts.
US -4 Shoreline Blvd. Median Islands (El Camino Real to Villa Street)
Renovate the existing median islands on Shoreline Blvd. from El
Camino Real to Villa Street by updating the hardscape, landscape and
irrigation system.
$1,250,000
$1,060,000
$2,290,000
$473,000
US -5 Gateway Signage, Design and Construction $322,000
Study, design, and construct gateway signs in several highly
visible /well travelled locations throughout the City. Depending on the
scope of the project, costs could range between $181,000 and
$322,000.
US -6 Calderon Avenue Bike Lane - Phase I (from Villa Street to Mercy
Street)
Provide a designated bicycle path on Calderon Avenue that will
conform to the Calderon Street Master Plan
US -7 Calderon Avenue Bike Lane - Phase II (from Mercy Street to El
Camino Real)
Provide a designated bicycle path on Calderon Avenue that will
conform to the Calderon Street Master Plan
Page 1
$234,000
$116,000
Unscheduled Projects
Projects moving from the Unscheduled Projects List to the Five -Year CIP will require updated cost estimates.
Item Project Description Estimated Cost
US -8 Rengstorff Avenue Adaptive Signal System $930,000
Install adaptive traffic signal technology, including a new signal
interconnect system along Rengstorff Avenue, from Montecito Avenue
to Garcia Avenue /Amphitheatre Parkway.
US -9 Rose Avenue Sidewalk Project (from Fordham Way to Miramonte $1,050,000
Avenue)
Install sidewalks and improve street drainage along Rose Avenue to
provide safe walking routes to neighborhood schools.
US -10 Pond 4 Water Level Reduction TBD
Reduce the water level in pond 4 at the Shoreline Golf Course, from
hole #4 to the bridge by the first tee. Work on this project can begin
after Alternative 1 from the Recycled Water Feasibility Study is
complete.
US -11 Golf Course Driving Range Regrading Plan $325,000
Add soil to the existing surface of the golf course driving range, install
new drainage system and irrigation for entire range to sustain grass,
install new safety fences to both sides, relevel the teaching tent,
prepare the top soil and seed the range for new grass.
US -12 Calderon Median (Dana to Evelyn) $450,000
Install raised medians and left turn pockets to reduce pavement and
provide landscaping.
US -13 Middlefield Road Median Refurbishment (Moffett to Shoreline) $700,000
Refurbish median landscaping and irrigation.
US -14 Easy Street /Gladys Intersection Reconfiguration $300,000
Revise curb return to make intersection at 90- degree angle from Easy
Street to Gladys.
Page 2
Unscheduled Projects
Projects moving from the Unscheduled Projects List to the Five -Year CIP will require updated cost estimates.
Item Project Description Estimated Cost
US -15 Irrigation Pump Station - Upgrades and Additions
Design and construct improvements for the irrigation pump station to
enhance reliability and efficiency.
US -16 Park Dr./Miramonte Ave. Intersection Realignment
Remove existing traffic island, realign Miramonte Ave., relocate
sidewalk, streetlights, curb ramp and storm drain modifications.
US -17 N/E Corner Moffett Blvd. /Central Expressway. Eliminate Free
Right -turn Lane
Improve pedestrian safety crossing Central Expressway to Caltrain,
Light Rail and the Adobe Building.
US -18 Light Rail Trail Lighting, Pacific Drive to MOC
Landscaping and fencing to improve safety and appearance of trail.
US -19 Eliminate Downtown Storm Drain Cross Culverts
Replace City's surface drain pipes at intersections in the downtown
area by installing catch basins, laterals and extending storm drain
pipes, reconforming the street grade and constructing curb ramps.
US -20 Upgrade Shoreline Blvd. Landscaping on Overpass over Central
Expressway
Renovate the County - installed landscaping within the cloverleaf,
upgrade the irrigation system and the pathway lighting along all four
sides of the overpass to improve appearance along this major entrance
to the downtown area.
US -21 Upgrade Whisman Road Landscaping on Central Expressway
Embankments
Renovate County- installed landscaping along the embankments and
upgrade the irrigation system.
Page 3
$700,000
$250,000
$500,000
$300,000
$3,200,000
$1,000,000
$750,000
Unscheduled Projects
Projects moving from the Unscheduled Projects List to the Five -Year CIP will require updated cost estimates.
Item Project Description Estimated Cost
US -22 Rex Manor Park Expansion $650,000
Improve neighborhood park facilities by increasing size from .41 acres
to .85 acres.
US -23 Landels Trail /Pathway Reconstruction, Design $200,000
Design pathway and trail access at Landels School to Stevens Creek
Trail.
US -24 Pedestrian Bridge Over Central Expressway Lighting $200,000
Install lighting on Stevens Creek Trail bridge crossing Caltrain tracks,
Central Expressway, and Evelyn Avenue.
US -25 Shoreline Clubhouse Parking Lot Reconstruction $525,000
Reconstruct the parking lot, restore the surface drainage system,
replace the median island landscaping and restripe the parking lot.
US -26 Stevens Creek Trail: Dale Avenue /Heatherstone Way to Mountain $15,000,000
View High School, Construction
Construction of pedestrian/bike trail from Dale/Heatherstone
neighborhood to trailhead at Mountain View High School.
US -27 Library Remodel, Construction $1,418,000
Construction of Library space renovations to meet current community
needs, as detailed in Appendix 4 of this document.
US -28 Center for the Performing Arts MainStage Sound System
Upgrade existing wiring, replace all patch bays with a digital console,
replace speakers, amplifiers, and processors.
US -29 Downtown Street Sign Program — El Camino Signs
Installation of five remaining directional signs from Project 06 -37,
Downtown Street Sign Program. The signs were manufactured as part
of the original project but have not been installed.
Page 4
$225,000
$63,000
Unscheduled Projects
Projects moving from the Unscheduled Projects List to the Five -Year CIP will require updated cost estimates.
Item Project Description Estimated Cost
US -30 Shoreline Boulevard Pathway (Villa St to Wright Ave),
Construction
Construction of pathway and connection improvements for bicycles
and pedestrians along Shoreline Boulevard between Villa Street and
Wright Avenue.
US -31 Facilities Major Planned and Emergency Repairs
Replacement, repair, and /or upgrades to access and other control
systems at City Hall, Center for the Performing Arts, Library, Senior
Center, and Community Center; roofing replacements /repairs at Fire
Station No. 3 and MOC Administration; carpeting replacement at
Police /Fire Administration, MOC Administration, Whisman Sports
Center, Mountain View Sports Pavilion; exterior painting of Whisman
Sports Center and Mountain View Sports Pavilion; remodeling of Fire
Station No. 1 kitchen; repair of Civic Center Plaza grout; and other
needed repairs /replacements at other City facilities.
US -32 Castro Park Restroom
Restroom facilities at Castro Park for youth sports participants. To be
coordinated/scheduled as a part of the MV Whisman School District's
plans to approve facilities at the Huff, Landels and Castro School
Park's during the next several years.
US -33 Rengstorff Aquatics Center — Building Design and Construction
Design and construction of the remodel of the existing Aquatics Center
building, including reconfiguring most spaces in the building. Includes
an entirely new plumbing system in the building and major repairs to
the existing roof, a new electrical service to the building, and includes
the renovation of the public restrooms that are accessed from the
outside of the Aquatics Center building. The project does not include
any work on the existing pools.
Page 5
$2,100,000
$1,225,000
$430,000
$8,400,000
Unscheduled Projects
Projects moving from the Unscheduled Projects List to the Five -Year CIP will require updated cost estimates.
Item Project Description Estimated Cost
US -34 Rengstorff Aquatics Center — Pool Design and Construction $3,300,000
Design and construct new pools, new pool play structure, a new pool
deck, fences and lighting, and new shade structures for the pool deck at
the Rengstorff Aquatics Center. The budget includes the demolition of
the existing pool and deck area. The scope assumes that the existing
pool mechanical equipment will be salvaged and not replaced.
US -35 Rengstorff Park Maintenance Building/Restrooms — Design and $3,750,000
Construction
Demolish existing Rengstorff Park Maintenance /Ranger Building and
attached public restrooms, as well as the adjacent maintenance vehicle
parking area, and design and construct a new maintenance building
near the group picnic area parking lot. Includes providing electrical
power, as well as water and sewer service, to the new building. The
budget does not include the subsequent construction of additional
parking in the location of the demolished old Maintenance Building.
US -36 Rengstorff Park Tennis Building — Design and Construction $1,850,000
Design and construct a new restroom/ storage building near the tennis
courts to replace the existing tennis building. This project includes the
demolition of the existing Rengstorff Park tennis building. The new
tennis building will include public restrooms as part of the building
and a small area to be used for storage. There currently are no sewer
lines running to the tennis building; as part of this project, a new sewer
line will need to be installed.
Total of Unscheduled Projects $55,536,000
Page 6
Active Projects
All numbers are in thousands (1,000)
Project
Number
Project Title
Sponsor
Department
Total
Budget
Encumbrances
at 3/31/2014
Balance at
3/31/2014
02 -42
Charleston East Site - Post Marketing Activities
Comm. Dev.
1,765
9
372
03 -36
New Stormwater Regulations
Public Works
100
0
74
04 -29
Bubb Park and Huff Park Restrooms
Public Works
633
15
237
05 -39
Recycled Water Distribution System Construction
Public Works
5,266
133
489
06 -25
Facilities Major Planned and Emergency Repairs
Public Works
1,920
15
88
07 -18
2006 -07 Information Services Computer Projects
IT
635
26
405
07 -35
Stevens Creek Trail, El Camino Real to Dale /Heatherstone, Design
Public Works
1,200
6
21
07 -42
Police/Fire Building Interior Refurbishment
Public Works
400
58
0
07 -43
Council Chambers Technology Update
City Clerk
655
5
64
07 -46
Caltrain Station Parking Deck, Engineering/Environmental Review
Public Works
455
361
2
08 -18
2007 -08 Information Services Computer Projects
IT
707
13
196
08 -27
Permanente Creek Improvements Design (SCVWD)
Public Works
175
7
44
08 -35
Restroom Facility at Dog Park
Comm. Svcs.
90
65
22
08 -99
General Plan
Comm. Dev.
2,691
176
43
09 -18
Information Technology Computer Projects
IT
785
11
46
09 -19
Biennial Park Renovations/Improvements
Comm. Svcs.
125
2
26
09 -24
Rengstorff Park Master Plan
Comm. Svcs.
464
5
83
09 -26
Permanente Trail Charleston Road Undercrossing Feasibility Study
Public Works
280
19
15
09 -28
Rengstorff Avenue Grade Separation/High Speed Rail Coordination
Public Works
350
85
29
09 -29
NASA -Ames Bayshore Lightrail Station Pedestrian Access Study
Comm. Dev.
240
27
10
09 -30
Modification to Alleyway Behind 200 Block of Castro Street
Comm. Dev.
50
3
47
09 -35
Install New Radio System Improvements and Monopole
Police
330
16
246
09 -44
Mariposa/W. Dana Park, Design and Construction
Comm. Svcs.
1,412
4
19
10 -11
2009 -10 Developer Reimbursements
Public Works
105
5
72
10 -18
Information Technology Computer Projects
IT
431
17
262
10 -28
California Street Rule 20A Underground Utility District No. 40
Public Works
55
3
41
10 -30
CPA- SecondSta e Support Space Addition, Design
Public Works
335
13
21
10 -33
AB 2466 Renewable Energy Facility Evaluation
Public Works
150
6
92
10 -34
Greening the Library
Public Works
140
8
127
10 -35
Create Zero Waste Action Plan
Public Works
230
28
0
10 -39
California/Escuela, Califomia/Ortega and Whisman/Middlefield Traffic
Signal Modifications
Public Works
1,359
653
65
10 -40
North Shoreline Boulevard (in the Park) Storm Drainage Rehabilitation
Public Works
887
80
666
10 -47
Moffett Gateway Property - Site Security and Corrective Action
Public Works
265
10
161
10 -49
Project Readiness Initiative
Public Works
100
6
1
11 -04
2010 -11 Water System Improvements
Public Works
310
13
18
11 -05
2010 -11 Wastewater System Improvements
Public Works
140
12
37
11 -17
1 Shoreline Infrastructure Maintenance
Public Works
210
4
69
Page 1
Active Projects
All numbers are in thousands (1,000)
Project
Number
Project Title
Sponsor
Department
Total
Budget
Encumbrances
at 3/31/2014
Balance at
3/31/2014
11 -18
Information Technology Computer Projects
IT
575
278
96
11 -27
Library Space Modifications, Design and Phase I
Public Works
311
18
270
11 -31
Vassar Avenue Reconstruction, Design
Public Works
180
11
116
11 -33
Athletic Field, Construction
Public Works
15,100
590
12,452
11 -34
Stevens Creek Trail Landscaping Improvements South of ECR
Public Works
93
5
82
11 -35
Stevens Creek Trail Access Point Improvements North of ECR
Public Works
170
1
19
11 -36
Improvements to Open Space at Bonnie and Beatrice Streets
Comm. Svcs.
32
2
28
11 -37
Highway 101 Auxiliary Lanes Coordination
Public Works
100
4
55
11 -38
Highway 85 Noise Barrier Study
Public Works
200
12
188
11 -40
Acquisition 449 Franklin Street
Public Works
1,635
17
109
11 -41
Landfill Microturbine Replacement
Public Works
558
10
30
11 -43
Vehicle Emissions Reduction VERBS Program
Public Works
565
135
28
11 -44
Central Expressway Sidewalks, Gemini Avenue to Moffett Blvd.
Public Works
625
55
437
11 -45
North Bayshore Precise Plan
Comm. Dev.
1,440
730
98
12 -02
11 -12 Traffic Signal and Street Light Pole Replacements/Modifications
Public Works
192
34
0
12 -04
11 -12 Water System Improvements
Public Works
314
27
9
12 -05
11 -12 Wastewater System Improvements
Public Works
141
9
132
12 -07
11 -12 Parks Pathway Resurfacing
Comm. Svcs.
73
2
26
12 -11
11 -12 Developer Reimbursements
Public Works
108
7
101
12 -13
11 -12 Landfill Gas /Leachate System Repairs & Improvements
Public Works
119
32
0
12 -15
11 -12 Annual Traffic Studies/NTMP Improvements
Public Works
119
46
12
12 -17
Shoreline Infrastructure Maintenance
Public Works
216
46
138
12 -18
Information Technology Computer Projects
IT
800
57
329
12 -19
Biennial Median Renovations and Roadway Landscape Renovations
Comm. Svcs.
65
12
20
12 -21
Miscellaneous Water Main/Service Line Replacement
Public Works
1,335
61
24
12 -22
Miscellaneous Storm/Sanitary Sewer Main Replacement
Public Works
1,497
108
299
12 -24
Installation of ADA Curb Ramps, Phase VII
Public Works
114
25
80
12 -26
11 -12 Annual New Energy Conservation Measures
Public Works
81
12
46
12 -28
Police /Fire Administration Building Refurbishment
Public Works
901
59
666
12 -29
Mechanical System Replacement at Eagle and Rengstorff Pools
Comm. Svcs.
1,133
26
124
12 -30
Vassar Avenue Reconstruction, Construction
Public Works
400
24
373
12 -31
Induction Lighting Replacements, Phase 1
Public Works
700
430
254
12 -32
Middlefield Road Median Islands Reconstruction, Easy Street to Shoreline
Blvd.
Public Works
883
110
706
12 -33
Critttenden Park (West Field) Turf Replacement, Design and Construction
Comm. Svcs.
1,485
90
1,386
12 -34
Parks and Trails Maintenance Projects
Public Works/
Comm. Svices
208
3
52
12 -36
Rock Church Refurbishment and Modification
Public Works
1 2,600
2,2231
121
Page 2
Active Projects
All numbers are in thousands (1,000)
Project
Number
Project Title
Sponsor
Department
Total
Budget
Encumbrances
at 3/31/2014
Balance at
3/31/2014
12 -37
Microfiche to Digital Imaging Conversion
IT
525
425
61
12 -38
Alignment/Constructability Study for Utility Crossing Replacements at
Hwy 101 and 85
Public Works
134
8
120
12 -40
Recycled Water System Expansion Feasibility Study
Public Works
300
30
32
12 -43
Moffett Gateway Property - Preparation for Development
Public Works
725
223
115
12 -45
Regional Public Safety Automated Information Systems
Public Works
3,262
1,818
12
12 -46
Shoreline Sewer Line Rehabilitation
Public Works
2,941
4
60
12 -48
Shoreline Sea Level Rise Study
Public Works
460
17
28
13 -01
Street Resurfacing Program
Public Works
698
7
104
13 -02
Traffic Signal and Street Light Pole Replacements/Modifications
Public Works
114
4
19
13 -04
Water System Improvements
Public Works
320
45
153
13 -05
Wastewater System Improvements
Public Works
144
12
130
13 -06
Concrete Sidewalk/Curb Repairs
Public Works
276
13
201
13 -07
Parks Pathway Resurfacing
Comm. Svcs.
75
0
4
13 -08
Shoreline Pathway, Roadway, Parking Improvements
Comm. Svcs.
177
11
166
13 -09
Forestry Maintenance Program and Street Tree Replanting
Comm. Svcs.
287
3
2
13 -11
Developer Reimbursements
Public Works
112
7
105
13 -13
Landfill Gas /Leachate System Repairs & Improvements
Public Works
121
7
16
13 -15
Annual Traffic Studies/NTMP Improvements
Public Works
121
49
63
13 -17
Shoreline Infrastructure Maintenance
Public Works
221
42
174
13 -18
Information Technology Computer Projects
IT
506
111
222
13 -19
Biennial Park Renovations/Improvements
Comm. Svcs.
99
6
90
13 -20
Biennial Good Neighbor Fence Replacements
Comm. Svcs.
33
1
22
13 -21
Miscellaneous Water Main/Service Line Replacement
Public Works
1,665
176
1,444
13 -22
Miscellaneous Storm/Sanitary Sewer Main Replacement
Public Works
1,435
162
1,229
13 -24
Biennial ADA Improvements to City Facilities
City Mgr.
83
5
78
13 -25
Annual New Energy Conservation Measures
Public Works
166
27
55
13 -27
City Bridges and Culverts Structural Inspections
Public Works
90
34
1
13 -28
Dana Street Reconstruction
Public Works
225
51
157
13 -29
Residential Parking Permit Program Study
Public Works
32
2
26
13 -30
Shoreline Boulevard Adaptive Signal System
Public Works
1,343
81
1,250
13 -31
Shoreline Golf Links Improvements
Comm. Svcs.
160
47
16
13 -32
Center for the Performing Arts (CPA) Theater Seat and Carpeting
Replacement
Comm. Svcs.
302
1
16
13 -33
Center for the Performing Arts (CPA) SecondStage Tension Grid
Installation
Comm. Svcs.
242
189
41
13 -34
Landels Park Restroom
Public Works
360
21
325
13 -36
Fayette Park
Public Works
2001
45
109
13 -37
El Camino Real /San Antonio Precise Plan
Comm. Dev.
1,380
817
100
Page 3
Active Projects
All numbers are in thousands (1,000)
Project
Number
Project Title
Sponsor
Department
Total
Budget
Encumbrances
at 3/31/2014
Balance at
3/31/2014
13 -38
Immigrant House Move/Storage
Public Works
32
1
13
13 -40
Acquisition of 771 North Ren storff
Public Works
3,400
29
101
14 -01
Street Resurfacing Program
Public Works
844
50
769
14 -02
Traffic and Streetlight Improvements
Public Works
297
13
207
14 -03
Slurry Seal Program
Public Works
123
7
109
14 -04
Water System Improvements
Public Works
327
15
199
14 -05
Wastewater System Improvements
Public Works
146
9
137
14 -06
Concrete Sidewalk/Curb Repairs
Public Works
252
13
200
14 -07
Parks Pathway Resurfacing
Comm. Svcs.
76
5
71
14 -08
Shoreline Pathway, Roadway, Parking Improvements
Comm. Svcs.
180
11
169
14 -09
Forestry Maintenance Program and Street Tree Replanting
Comm. Svcs.
293
100
39
14 -10
Shoreline Landfill Cap Maintenance and Repairs
Public Works
124
3
33
14 -11
Developer Reimbursements
Public Works
112
7
105
14 -12
Street Lane Line and Legend Repainting
Public Works
39
2
35
14 -13
Landfill Gas /Leachate System Repairs & Improvements
Public Works
124
30
65
14 -14
Facilities Maintenance Plan
Public Works
513
30
3
14 -15
Annual Traffic Studies/NTMP Improvements
Public Works
124
8
116
14 -16
Maintenance Agreement for JPB/VTA Transit Center
Public Works
56
6
48
14 -17
Shoreline Infrastructure Maintenance
Public Works
225
14
211
14 -18
Information Technology Computer Projects
IT
330
84
112
14 -19
Biennial Median Renovations and Roadway Landscape Renovations
Comm. Svcs.
68
4
61
14 -20
Biennial Real Estate Technical and Legal Services
Public Works
68
9
56
14 -21
Miscellaneous Water Main/Service Line Replacement
Public Works
1,915
116
1,782
14 -22
Miscellaneous Storm/Sanitary Sewer Main Replacement
Public Works
1,440
88
1,350
14 -23
TDA Projects
Public Works
60
4
56
14 -24
Biennial Installation of ADA Curb Rams
Public Works
24
1
23
14 -25
Annual New Energy Conservation Measures
Public Works
84
27
9
14 -26
Biennial PMP Recertification
Public Works
66
3
50
14 -27
Tennis Court Resurfacing at Cooper, Stevenson, Sylvan, and Whisman
Comm. Svcs.
79
5
70
14 -28
Street Sign Replacements
Public Works
202
23
175
14 -29
Doane Avenue Reconstruction
Public Works
607
37
570
14 -30
Central Sewage Trunk Main - Inspection and Cleaning
Public Works
150
23
127
14 -31
West Sewage Trunk Main - Inspection and Cleaning
Public Works
200
12
188
14 -32
Sewage Pump Station Replacement Analysis
Public Works
2501
15
234
14 -33
Interceptor Force Trunk Main - Manhole Construction, Inspection and
Cleaning
Public Works
250
68
176
14 -34
1 Shoreline Maintenance Storage Plan
Public Works
676
125
543
14 -35
1 Safe Routes to Schools Education Program
Public Works
1 565
341
531
Page 4
Active Projects
All numbers are in thousands (1,000)
Project
Number
Project Title
Sponsor
Department
Total
Budget
Encumbrances
at 3/31/2014
Balance at
3/31/2014
14 -36
Modifications to Castro Street, between El Camino Real and Miramonte
Avenue
Public Works
950
57
884
14 -37
Resurfacing Segments of Rengstorff Avenue, Old Middlefield Way, and
Charleston Road
Public Works
1,318
80
1,223
14 -38
Permanente Creek Trail - Charleston Road and Amphitheatre Parkway
Crossings, Design
Public Works
605
219
360
14 -39
NASA Ames Bayshore Light Rail Station Pedestrain Access
Improvements, Design
Public Works
475
29
446
14 -40
Pedestrian/Bicycle Safety Improvements
Public Works
300
18
282
14 -41
California Street/Escuela Avenue Improvements
Public Works
250
15
224
14 -42
Update Bicycle Transportation Plan
Public Works
200
162
37
14 -43
Shoreline Transportation Improvements/North Bayshore Area Precise Plan
Coordination
Public Works
1501
91
41
14 -44
Shoreline Transit Corridor, Feasibility Study
Public Works
600
435
65
14 -45
Downtown Bike Racks
Public Works
50
2
37
14 -46
Caltrain Modernization Program - Environmental Review
Public Works
150
99
51
14 -47
Sea Level Rise Flood Protection Coordination
Public Works
100
5
79
14 -48
Utility Capacity and Alignment Engineering Studies - El Camino Real and
San Antonio Change Areas
Public Works
320
34
277
14 -49
Water and Sewer Capacity Analyses
Public Works
150
9
141
14 -50
Fire Station Alerting System
Fire
253
15
238
14 -51
MainSta e Equipment Re lacement
Comm. Svcs.
338
231
27
14 -52
Landfill Gas Flare Replacement
Public Works
1,065
532
503
14 -53
Shoreline Boulevard Crosswalk Improvements
Public Works
150
591
84
14 -54
McKelvey Park Detention Basin SCVWD Coordination
Public Works
350
21
322
Adopted Mid -Year Capital Improve ent Projects
14 -55
School Zone Speed Limit - -15 mph Sign Installation
Public Works
137
8
123
14 -56
Technology Projects Goo le Grant
IT
500
0
500
14 -57
Middlefield Light Rail Station Bike Share Station
Public Works
192
0
192
Total of Active Projects
102,772
14,890
44,740
Page 5
Projects to Close
All numbers are in thousands (1,000)
CIPs to be closed on June 30, 2014
Prgject
Number
Pro'ect Title
Sponsor
Department
Total
Budget
Encumbrances
at 3/31/2014
Balance at
3/31/2014
03 -23
Fire Station No. 5 Design
Public Works
1,870
8
124
06 -33
Permanente Creek Ped/Bike Overcrossing Highway 101, Construction
Public Works
12,230
14
216
07 -38
ILibrary Space Reallocation
Public Works
1,8921
0
0
08 -29
2007 -08 Facilities Major Planned and Emergency Repairs
Public Works
225
1
0
09 -32
Fire Station No. 5, Construction
Public Works
7,000
22
331
09 -43
Shoreline Park Wildlife Management
Comm. Svcs.
320
0
3
10 -02
2009 -10 Traffic Signal Replacements/Modifications
Public Works
155
0
1
10 -04
2009 -10 Water System Improvements
Public Works
300
0
0
10 -17
Shoreline Infrastructure Maintenance
Public Works
510
52
81
10 -25
Annual ADA Improvements to City Facilities
Public Works
80
0
0
10 -26
Installation of ADA Curb Ramps, Phase V
Public Works
50
1
8
10 -27
2009 -10 Annual New Energy Conservation Measures
Public Works
159
16
0
10 -29
Library Automated Materials Handling System, Phase II, Design &
Construction
Public Works
147
0
0
10 -41
Del Medio Park, Design and Construction
Public Works
1,101
0
0
10 -42
Stevens Creek Trail, Sleeper to Dale /Heatherstone, Construction
Public Works
5,515
102
256
10 -48
Shoreline Boulevard Sidewalk Replacement
Public Works
2,151
928
355
11 -02
2010 -11 Traffic Signal Replacements/Modifications
Public Works
210
0
0
11 -08
2010 -11 Shoreline Pathway, Roadway, Parking Improvements
Comm. Svcs.
170
48
1
11 -13
2010 -11 Landfill Gas /Leachate System Repairs & Improvements
Public Works
78
0
0
11 -14
2010 -11 Facilities Maintenance Plan
Public Works
505
10
0
11 -15
2010 -11 Annual Traffic Studies/NTMP Improvements
Public Works
107
0
0
11 -19
Biennial Park Renovations /Improvements
Comm. Svcs.
85
0
4
11 -21
Miscellaneous Water Main/Service Line Replacement
Public Works
1,245
0
1
11 -22
Miscellaneous Storm/Sanitary Sewer Main Replacement
Public Works
1,198
0
0
11 -24
Biennial ADA Improvements to City Facilities
City Mgr.
80
43
0
11 -25
Installation of ADA Curb Ramps, Phase VI
Public Works
395
35
45
11 -26
2010 -11 Annual New Energy Conservation Measures
Public Works
171
20
0
11 -28
Fire Station No. 4 Drill Grounds Modification
Public Works
228
0
0
11 -30
San Luis Avenue Reconstruction
Public Works
834
4
65
11 -39
Church Street Improvements, Castro to Calderon
Public Works
975
8
22
11 -42
Michael's Facility Upgrades and Repairs
Public Works
460
4
1
12 -06
11 -12 Concrete Sidewalk/Curb Repairs
Public Works
330
2
18
12 -08
11 -12 Shoreline Pathway, Roadway, Parking Improvements
Comm. Svcs.
173
145
15
12 -09
11 -12 Forestry Maintenance Program and Street Tree Replanting
Comm. Svcs.
281
15
2
12 -12
11 -12 Street Lane Line and Legend Repainting
Public Works
50
2
28
Page 1
Projects to Close
All numbers are in thousands (1,000)
CIPs to be closed on June 30, 2014
Project
Number
Project Title
Sponsor
Department
Total
Budget
Encumbrances
at 3/31/2014
Balance at
3/31/2014
12 -14
11 -12 Facilities Maintenance Plan
Public Works
487
4
0
12 -16
11 -12 Maintenance Agreement for JPBNTA Transit Center
Public Works
54
0
42
12 -20
IBiennial Real Estate Technical and Legal Services
Public Works
651
7
9
12 -25
Biennial PMP Recertification
Public Works
64
2
28
12 -27
Cape Seal Program
Public Works
575
6
22
12 -35
Permanente Creek Trail: Old Middlefield Way to Rock Street
Public Works
521
29
54
12 -39
Landfill Infrastructure Master Plan Study
Public Works
250
5
79
12 -41
Trash Capture Demonstration Project
Public Works
275
78
16
12 -42
Shoreline Transportation Study
Public Works
500
2
29
12 -44
Mayfield and Whitney Parks Design
Public Works
425
421
0
12 -47
Incident Management and Command Training Simulator
IT
229
0
7
13 -03
Slurry Seal Program
Public Works
251
7
48
13 -10
Shoreline Landfill Cap Maintenance and Repairs
Public Works
121
0
0
13 -12
Street Lane Line and Legend Repainting
Public Works
336
4
56
13 -14
Facilities Maintenance Plan
Public Works
496
2
0
13 -16
Maintenance Agreement for JPBNTA Transit Center
Public Works
55
4
44
13 -23
TDA Project - Mercy/Calderon Intersection Traffic Calming Improvements
Public Works
130
0
1
13 -26
1 Downtown Parking Structure and Lots Restriping
Public Works
88
2
27
13 -35
Mayfield Development Traffic Improvements and Monitoring
Public Works
560
560
0
13 -39
Berlin Wall
Public Works
50
1
11
Total of Closed Projects
46,809
2,613
2,055
Page 2
APPENDIX LIST
Large Sewer Main Rehabilitation Projects
2. Water Meter Replacement Plan
3. Information Technology Project Request for Fiscal Year 2014 -15
4. Library CIP Proposal (Unscheduled Project US -27)
Appendix 1
CITY OF MOUNTAIN VIEW
MEMORANDUM
Public Works Department
DATE: February 28, 2014
TO: Michael A. Fuller, Public Works Director
FROM: Gregg A. Hosfeldt, Assistant Public Works Director
SUBJECT: Large Sewer Main Rehabilitation Projects
The purpose of this memo is to provide background information on anticipated sewer
rehabilitation projects.
BACKGROUND
The City's wastewater collection system is comprised of 157 miles of pipe ranging from
4" to 48 ", with 68 percent of the lines installed in the 1950s and 1960s. Wastewater
collected from residential and business customers is routed to three large pipelines
(trunk mains) in the North Bayshore Area, consolidated at the City's Sewage Pump
Station, and pumped into an interceptor main which flows under gravity to the
Regional Water Quality Control Plant in Palo Alto. Attachment 1 shows the alignment
of the trunk mains, the interceptor main, and the location of the Sewage Pump Station.
The majority of the trunk main infrastructure was installed in the 1950s and 1960s, with
limited segments replaced in the 1970s and 1980s. The 2010 Sewer System Master Plan
included an analysis of the City's sewer infrastructure based on age, pipe materials, soil
corrosivity, and accessibility for repairs. Based on this analysis, large segments of the
east and west mains were identified as nearing the end of their service life (less than 25
percent remaining), with other portions having 25 percent to 50 percent of service life
remaining. Because the trunk mains are a critical component of the sewer system and
failures could cause significant damage, the City is conducting additional evaluations of
pipe condition to determine the optimal timing and estimated costs of rehabilitation to
ensure uninterrupted and reliable wastewater service. In addition to extending the
service life of the mains by approximately 50 years, the rehabilitation projects reduce
the infiltration of groundwater into the sewer system, preserving sewer capacity for
wastewater flows. Reducing groundwater infiltration may also reduce the amount of
salts and dissolved solids entering the wastewater stream, potentially reducing the
salinity of the City's recycled water.
Large Sewer Main Rehabilitation Projects
February 28, 2014
Page 2 of 3
EAST TRUNK MAIN
The east trunk main extends from Highway 101 to the Sewage Pump Station, running
through the NASA Ames property and the Shoreline Golf Links. The main was
installed in the 1960s and includes 17,000' of pipe ranging in diameter from 27" to 42 ".
Approximately 3,800' of this main between Stevens Creek and the Sewage Pump
Station was relined in 2012, extending the service life by approximately 50 years. An
additional 4,700" of pipeline east of Stevens Creek was identified in the Master Plan as
having a remaining service life of 0 percent to 25 percent.
WEST TRUNK MAIN
The west trunk main extends from Highway 101 to the Sewage Pump Station, running
under North Bayshore properties and the Shoreline Golf Links. The main was installed
in the 1950s and includes 4,250' of pipe ranging in diameter from 30" to 33 ". Although
the condition of this main is unknown, the pipeline was identified in the Master Plan as
having a remaining service life of 0 percent to 25 percent, and staff anticipates some
rehabilitation/ replacement work will be necessary in the next 10 years. The west trunk
main will be televised by a contractor in the next two months, after which staff will
develop updated capital project recommendations.
CENTRAL TRUNK MAIN
The central trunk main extends from Highway 101 to the Sewage Pump Station,
running under Shoreline Boulevard to an intersection with the east trunk line. The
main was installed in the 1950s, 1970s, and 1980s, and includes 7,800' of pipe ranging in
diameter from 18" to 27". Although approximately 300' of this pipe was relined in 2012
(as part of the east trunk main rehabilitation project), the condition of the majority of the
pipeline is unknown but, because of its age, staff anticipates some rehabilitation/ repair
work near Highway 101 will be needed in the next five years. The central trunk main
will be televised by a contractor in the next two months, after which staff will develop
updated capital project recommendations.
INTERCEPTOR MAIN
The interceptor main extends from the Sewage Pump Station to the western City limit,
and continues to the Regional Water Quality Control Plant in Palo Alto. The main was
installed in the 1960s and includes 3,800' of pipe ranging in size from 36" to 42 "; the
main was identified in the Master Plan as having a remaining service life of 0 percent to
25 percent.
Large Sewer Main Rehabilitation Projects
February 28, 2014
Page 3 of 3
Because there are no manholes in this main, staff is unable to fully assess pipe
condition. A current capital project is funding installation of four manholes; after
construction is complete, the pipe will be inspected. Based on evidence of pipe damage
near the Sewage Pump Station, staff anticipates planning rehabilitation/ repair work
will be likely in the next three years.
CAPITAL PROTECT PLAN
Based on current information, I am tentatively planning a rehabilitation/ replacement
design project for the interceptor main and central trunk main in Fiscal Year 2014 -15
and rehabilitation of the interceptor main in Fiscal Year 2015 -16. Additionally, because
of concerns regarding the condition of the central trunk main near Highway 101, I
anticipate a rehabilitation project will be needed in Fiscal Year 2017 -18. I have also
tentatively scheduled longer -term (beyond the five -year planning horizon)
rehabilitation projects for the west and east trunk lines. Attachment 2 illustrates the
preliminary schedule and cost for these projects.
I will continue to refine this plan as Public Services receives additional information
regarding pipe conditions.
GAH/ 2/ PSD
761- 02- 28 -14M -E
Attachments: 1. Sewer System Map
2. Preliminary Capital Project Schedule
Interceptor Main
To Treatment at
PARWPCP
Alma M
ri
Shoreline Sewage
Wastewater Lift Station
West Trunk
,Sewer
i-1
Feet
0 3,000 6,000
Central Trunk
Sewer
In
City of Mountain View Boundary
Parcels
Collection System Sewer
Collection System Trunk Sewer
EastlTrunk
Sewer I
Lift
Moffett Field
Moffett Field Meter
A
N Infrastructure
City of Mountain View
Sewer System Master Plan
Collection System Overview
August 2010
Figure 2 -1
i
cu
SEWER REHABILITATION PROJECTS - PRELIMINARY PLAN
rt
K
n
Fiscal Year
Project
Cost
0
2014 /
15
Interceptor and Central Main Rehabilitation - Design
324,000
(replaces planned project 15-29)
2015 /
16
Interceptor Main Rehabilitation - Construction
3,899,000
2016 /
17
-
2017/
18
Central Trunk Line - Construction
3,588,000
2018 /
19
-
2019 /
20
West Trunk Line - Design / Construction
4,000,000
2020 /
21
-
2021 /
22
East Trunk Line RCP - Design / Construction
5,225,000
2022/
23
-
2023 /
24
-
2024 /
25
-
2025 /
26
East Trunk Line VCP - Design / Construction
8,947,000
25,983,000
Cost estimates are inflated 3 % annually
Appendix 2
CITY OF I IO NTAI N VIEW
MEMORANDUM
Public Works Department
DATE: February 14, 2014
TO: Michael A. Fuller, Public Works Director
FROM: Gregg A. Hosfeldt, Assistant Public Works Director
SUBJECT: Water Meter Replacement Plan
The purpose of this memo is to provide background information on the City's water
meter reading program and request an increase of $200,000 in the annual Water System
Improvement Capital Improvement Project to fund replacement of meters based on
anticipated meter life.
BACKGROUND
The Public Services Division/ Utilities Section is responsible for reading and
maintaining the City's inventory of 17,630 water meters. The majority of the meters are
3/4" and 1" serving single- and multi - family residential customers (15,480 meters).
Other meter sizes include 1.5" and 2 ", used mainly for commercial/ industrial and
multi - family customers, and irrigation services (1,871 meters), and 3" to 8" (279 meters)
serving large apartment complexes and commercial/ industrial accounts.
Approximately 73 percent of the City's water meters are more than 15 years old. The
American Water Works Association (AWWA) indicates the optimal operating life of a
meter is 15 years. While meters function beyond this time frame, they gradually under -
record water use, reducing water sales revenue and increasing the amount of "lost" or
unaccounted for water. Based on manufacturer testing and AWWA research, water
consumption is underreported by 2 percent to 5 percent in meters 20 to 30 years old.
METER READING PROCESS
The City collects water use data by manually reading each meter and entering the
readings into a handheld computer for transmittal to the City's billing system, a process
that has been in place since the mid- 1990s. Meters are grouped into 90 routes which are
generally based on distinct areas or neighborhoods. A limited number of routes,
containing approximately 650 of the largest commercial/ industrial meters, are read
Water Meter Replacement Plan
February 14, 2014
Page 2 of 3
monthly; the remaining routes are read every two months. Meter reading tasks
consume approximately 1.0 FTE.
All meters installed since 2007 (approximately 27 percent of the City's inventory) are
equipped with transmitters which allow reading by driving by the meters, and do not
require staff to exit vehicles or perform data entry. As meters are gradually replaced
throughout the City (by route), the need for manual reading is reduced. When all
remaining old meters have been replaced, all routes will be read in approximately seven
days per month, reducing meter reading obligations to approximately 0.4 FTE. These
meters are also capable of providing data collection via WiFi or cellular technology
(eliminating the need for drive -by reading) with no additional changes to the meter.
There would be additional costs for installing communication hardware at various
locations, but staff has not fully analyzed the costs and benefits of implementing
remote -read technology.
BENEFITS OF METER REPLACEMENT
There are numerous benefits to replacing the remaining old meters in the City's
inventory.
• The replacements will reduce the amount of unaccounted for or "lost" water. In
Fiscal Year 2012 -13, the City's unaccounted for water (water purchases less water
sales and other known uses) was approximately 7 percent. Although AWWA
standards indicate unaccounted for water should be 10 percent or less, it is likely
our lost water percentage will decrease as new meters are installed.
• Increasing the number of units sold will spread operating and capital costs over a
larger base, reducing per -unit water rates.
• The new meters will have transmitters that allow staff to drive by the meter and
collect readings using a laptop computer. The meters will also be capable of
providing data collection via WiFi or cellular technology (eliminating the need for
drive -by reading) with no additional changes to the meter.
• Use of remote -read meters will allow the City to provide detailed and timely
water - consumption information to utility customers through a third -party
software package. Water Conservation staff is currently managing a pilot
project through the City's Innovation Labs Program.
• Vehicle use and fuel consumption will be reduced, decreasing production of
greenhouse gases.
Water Meter Replacement Plan
February 14, 2014
Page 3 of 3
• Decreasing the time required to collect readings will facilitate monthly billing,
increasing the amount of interest generated for the Water Fund.
• Replacing old meters will ensure the City meets AWWA recommendations for
water meter service life.
REPLACEMENT TIMING AND CAPITAL IMPROVEMENT FUNDING
The value of the City's meter inventory (based on current replacement costs) is
approximately $5,000,000. The annual Water System Improvement CIP includes
funding of $100,000 for meter replacements, an amount adequate to replace only 2
percent of the inventory, resulting in a 50 -year replacement cycle.
The requested increase includes the cost of the meters, meter appurtenances, and sales
tax. The total annual funding of $300,000 will be adequate to replace meters on a 20-
year cycle. Although the AWWA indicates the optimal life of a meter is 15 years,
testing of the City's old meters indicates that a 20 -year operating life is a reasonable
expectation and meter accuracy does not significantly decrease before 20 years.
Accelerated Replacement Option
Staff reviewed the potential savings from replacing old meters on an accelerated basis
to reduce meter reading obligations. Because the meter reading staffing needs will be
reduced by only 0.6 FTE after all meters are replaced (from current staffing of
approximately 1.0 FTE to future staffing of 0.4 FTE), we do not anticipate being able to
reduce staffing when replacements are complete. The anticipated labor savings of 0.6
FTE will increase resources available for ongoing water system maintenance, and will
allow Public Services to address maintenance needs on the expanding recycled water
system using current staffing. Additionally, adopting a 20 -year replacement cycle will
allow the City to establish a consistent and sustainable level of annual meter
replacements, eliminating the need to fund periodic and costly City -wide replacement
projects.
GAH/ 7/ PSD
761- 02- 14 -14M -E
Appendix 3
CITY OF MOUNTAIN VIEW
MEMORANDUM
Information Technology Department
DATE: May 20, 2014
TO: City Council
FROM: Steve Rodriguez, Information Technology Manager
Roger R. Jensen, CIO /Information Technology Director
VIA: Daniel H. Rich, City Manager
SUBJECT: Information Technology Project Request for Fiscal Year 2014 -15
(Revised)
PURPOSE
This memo transmits the Capital Improvement Project (CIP) requests for the
Information Technology (IT) Department for Fiscal Year 2014 -15.
BACKGROUND
IT CIPs are identified as a single project, but will generally consist of subprojects.
Proposals for Fiscal Year 2014 -15 total $949,000 and are as follows:
New Projects
Work Order Management System, Phase I ($375,000) — Develop project to implement
modular- based, City -wide work order management system. Initial scope will include
modules to support the Urban Forestry, Fleet, Storm, Sewer, and Water Divisions, as
well as the City -wide permitting process. Additional components will be evaluated
during project development for future expansion of selected solution.
IFAS One Solution Upgrade ($300,000) —The City's IFAS Enterprise system provides
the financial system, including budget, accounting, purchasing, human resources, and
payroll. The City implemented IFAS in 1999 and this project would upgrade IFAS to
Sungard's "One Solution' platform and convert the relational database from Informix
to Microsoft SQL Server. This project will move the City's financial system to the latest
release version available and will provide additional features and ability to implement
additional workflow applications. The IFAS One Solution Upgrade project also
Information Technology Project Request for Fiscal Year 2014 -15 (Revised)
May 20, 2014
Page 2 of 3
includes some professional services for review of business processes and
implementation of changes. After reviewing the vendor's proposal and providing for
cost contingencies, the total for this fund has been adjusted from the $250,000 amount in
the earlier version of the IT CIP memo dated March 10, 2014.
IT City -Wide Apps ($50,000) — These project funds will be established to allow for rapid
deployment of minor technology projects as opportunities are identified. This will
ensure the City can continue its focus on using technology to enhance service levels and
availability of information to the public by establishing a funding source for these
projects.
PS Back -Up System ($53,000) —Implement an independent back -up system to be
installed and located at the City's secondary IT facility located in the Police /Fire
Administration Building to support the recently installed tri -City CAD public safety
systems. This back -up system will allow public safety staff to maintain continuity of
operations in the event of a critical system failure and retain an independent back -up
system by providing a mirror image of the public safety systems' operations to facilitate
a faster system- recovery time. Project funds will be combined with contributions from
the cities of Los Altos and Palo Alto as part of a shared procurement.
CAD Mobile Platform Access ($133,000) —This project will upgrade the modems in
Police vehicles to allow tablet devices to connect and provide access to CAD, RMS,
Smart Justice, and other applications. The Police Department intends to migrate to
technology that will allow Computer -Aided Dispatch (CAD), the Records Management
System (RMS), and the Evidence.com photo evidence system to be accessible as an
application on mobile devices. These mobile devices will allow for field personnel to
access data, including photos and documents that provide timely information to
enhance officer safety, reduce the amount of time subjects are detained, and enhance
the accuracy of assessing information related to wanted persons, missing and protected
persons, and sex offenders.
Council Chambers ($100,000) — Upgrade the Council Chambers audio and visual
technology, including, but not limited to, media /meeting management, hardware,
software, voting application, and speaking timer.
Amended Projects
Geospatial Information System (GIS) Phase III (Final) Upgrades ($75,000) —Phase III
of the GIS upgrade will continue the development of the GIS platform by expanding the
application pool to include advanced web -based mapping solutions and establish an
Information Technology Project Request for Fiscal Year 2014 -15 (Revised)
May 20, 2014
Page 3 of 3
ongoing data maintenance framework to ensure the GIS remains accurate and up to
date.
PSD Maintenance Management System( - $40,000) —These funds (CIP 4101805) will be
transferred to the "Work Order Management System, Phase I" project.
IFAS 7I Upgrade (- $37,000) —These funds (CIP 4081803) will be transferred to the "IFAS
One Solution Upgrade" project.
IFAS Time Online (-$60,000) —These funds (CIP 4081804) will be transferred to the
"IFAS One Solution Upgrade" project. The online timekeeping project is estimated to
be able to be accomplished with the funds remaining. After reviewing the online
timekeeping vendor's proposal and providing for cost contingencies, the total for this
fund has been adjusted from the $100,000 transfer amount in the earlier version of the
IT CIP memo dated March 10, 2014.
CONCLUSION
The funding requested will assist with City Council's technology goal for Fiscal Year
2014 -15 to:
Use technology to enhance customer service, efficiency, and advance the
mission of the organization.
RRJ -SR/ 7/ IT
450- 05- 20 -14M -E
Appendix 4
II { JJ�4ltl /Y�[ /�i ( t
.. 1. it ISif rr er�i4 �ST k+x1'f 4iY'
MEMORANDUM
DATE: February 27, 2014
TO: Dan Rich, City Manager
FROM: Rosanne Macek, Library Services Director
SUBJECT: Library CIP Proposal
PROJECT SUMMARY
This project would renovate areas of the Library in need of updating to meet current
community needs, including:
1. Expanding the children's services area into the adjacent media area
2. Expanding the existing community room into the adjacent media area
3. Creating a new, additional community room for adult programs
4. Creating seating area(s), three new study rooms, and consolidating the
information and technology desks on the second floor
5. Creating an additional reading area
The building will also be required to meet current accessibility requirements, which
may include an accessible van space in the underground parking garage, handrails and
barriers at the exterior stairs and ramp, and some new interior signage.
JUSTIFICATION/NEED
Introduction
The current Mountain View Public Library building was opened in 1997, based on a
building program that was completed 21 years ago in 1992. Because of dramatic
changes in use of the building, and omissions in the original plan, it is time to consider a
remodel to ensure that the service meets current community needs.
Library CIP Proposal - February 27, 2014 1 City of Mountain View
Changing Building Use
In the past 16 years since the library was opened, use of the building has increased
dramatically. The chart below compares use of the facility one year after it opened to
FYE June 30, 2013.
Mountain View Public Library
Then and Now
More residents are visiting the library, they're checking out more materials, they're
hanging out to study, and they're attending more classes and programs in the building.
The library has evolved into a community gathering space, which is a trend for public
libraries across the country.
Even though the library is offering information electronically via eBooks and databases, k
the print collection remains important. According to a recent study published in the
Los Angeles Times, 62% of the young people ages 16 to 24 said that they prefer printed
books to eBooks.1 While the print book collection is not expected to grow, it is not
expected to decrease dramatically within the next five years. However, based on
current usage, the magazine and DVD collections will probably become less important
in the coming years due to more current information available on the internet and the
use of streaming services for media.
The part of the library's service that has increased the most dramatically is program
attendance, for both children and adults. The library's mission of lifelong learning is
increasingly fulfilled through workshops and classes as well as via the collection.
Library Program Attendance
1999
2013
Increase
Library visits
528,083
855,854
+62%
Collection
264,275
330,562
+25%
Circulation
812,826
1,746,903
+115%
Program attendance
16,662
56,570
+240%
More residents are visiting the library, they're checking out more materials, they're
hanging out to study, and they're attending more classes and programs in the building.
The library has evolved into a community gathering space, which is a trend for public
libraries across the country.
Even though the library is offering information electronically via eBooks and databases, k
the print collection remains important. According to a recent study published in the
Los Angeles Times, 62% of the young people ages 16 to 24 said that they prefer printed
books to eBooks.1 While the print book collection is not expected to grow, it is not
expected to decrease dramatically within the next five years. However, based on
current usage, the magazine and DVD collections will probably become less important
in the coming years due to more current information available on the internet and the
use of streaming services for media.
The part of the library's service that has increased the most dramatically is program
attendance, for both children and adults. The library's mission of lifelong learning is
increasingly fulfilled through workshops and classes as well as via the collection.
Library Program Attendance
1 Tobar, Hector, "Young people prefer printed books to e- books; survey finds." Los Angeles Tunes, November 26,
2013.
F_
Library CIP Proposal - February 27, 2014 1 City of Mountain View
1999
2013
Increase
Children
16,177
38,947
+141%
Adults
485
4,404
+808%
1 Tobar, Hector, "Young people prefer printed books to e- books; survey finds." Los Angeles Tunes, November 26,
2013.
F_
Library CIP Proposal - February 27, 2014 1 City of Mountain View
Inadequate Children's Area
Because of cost constraints, the building was opened with inadequate space for children
and families. Of the total 60,000 square feet, only about 10% is devoted to the children's
area. Based on current library usage, about 80% of the program attendance and 45% of
the total circulation is from the children's department, yet so little of the building is
devoted to this important function. Informal feedback from a local architectural firm
reveals that of 4 new public libraries they designed, the average space devoted to
children's services was 22 %.
There were informal plans to eventually expand the children's area out into the parking
lot on the Franklin Street side, but that would be costly for the city and would eliminate
much - needed parking. Based on data from the California State Library for the other
communities near the same population as Mountain View, the median library square
footage is 48,941, with a mean of 41,500. With 60,000 square feet, Mountain View
already has a good -size library, so remodeling within the existing building footprint is
recommended as the most cost - effective plan to ensure the Library meets current
community needs.
RECOMMENDATION
The following space planning goals are recommended, in order of priority:
1. Expand the children's space into the adjacent media area, address noise from
first to second floor problem, move media to second floor, and consolidate
service points.
a. The children's space is too small to support the Library's service to youth
and families. It is recommended that this space be expanded into the
adjacent media area. This need was identified many years ago and there
is a current unscheduled project, US -27, in the CIP FY2013 -14 through FY
2016 -17.
b. Since the building was originally opened, there have been numerous.
complaints about the noise traveling from the first floor to the second floor
through the opening in the second floor above the current media area.
Expanding children's will make this problem worse, since children's
programs are quite noisy, and the adults using the second floor need quiet
study space. Therefore, it is recommended that this opening be.closed
and made into a structural floor, and that a wall be added between the
newly expanded children's space and the lobby. This not only addresses
the noise problem, but allows for useable square footage on the second
Library CIP Proposal - February 27, 2014 1 City of Mountain View
floor for additional seating. As above, this also has been a long -
recognized need, with, an unscheduled project, US -12.
c. Expanding the children's space will require that the adult media
collections be relocated to the second floor. With dramatic reductions in
the print reference collection, and the expectation that the media collection
will not grow, there is space to accommodate this.
d. Due to confusion experienced by the public between the welcome and
customer service desks, a consolidation of service points would be more
efficient for the public. The welcome desk would be removed, and its
functions would be incorporated into the customer service desk. With
expansion of the children's area, the children's reference desk would be
moved to the center of the newly- expanded space.
2. Increase programming space, including expanding the current community
room and capturing backroom space for an additional program room.
a. The existing community room is too small for most children's programs.
Friday morning story times often draw well over 300 people for two
sessions. And summer reading programs have been moved out into the
park to accommodate the large crowds. The current room would be
expanded into the adjacent media area, which will increase the space
approximately 540 square feet to about 1,695 square feet.
b. With attendance at adult programs increasing dramatically, there is a need
for a smaller program room for adult programs and other community
.meetings such as the Library Board. There are two options for this. One
would be to capture approximately 790 square feet in the first floor staff
area, but since this adjacent to the server and telecom room, it may not be
feasible. The likely space is on the second floor, where the back issues of
the magazines have been stored until recently. Because of the dramatic
drop uz use of this collection, most of it has been cleared out and digitized,
freeing up approximately 735 square feet for public use.
3. Add seating and study rooms on the second floor and consolidate service
points.
a. One of the concerns expressed in the Library Customer Survey was lack of
seating on the second floor. The building is often at capacity, with no
empty seats, if the open space is turned into a structural floor, additional
seating could be added.
Library CIP Proposal - February 27, 2014 1 City of Mountain View
b. Service points could also be consolidated to make space for three
additional study rooms, which are also at capacity.
4. Create an additional reading area.
a. The periodical back file room can be opened up to create an additional
reading area on the second floor, adjacent to the existing
periodical/ reading area. If the new community room is located in this
area (per 2b above), then the new reading area can be located in the staff
area on the first floor.
COST ESTIMATES
Complete Project
Expansion of children's and expansion of existing community room
Expansion of children's only, no community room expansion
Expansion of existing community room only
Option 1- Convert first floor staff area to small community room
Option 2 - Convert first floor staff area to reading room
Consolidate 2nd floor service desks, add seating and study rooms
Option 1- Convert periodicals back file room to seating area
Option 2 - Convert periodicals back file room to community room
$1,418,500
$1,020,000
$681,000
$232,000
$207,000
$193,000
$310,000
$200,000
$194,000
Note: We do have $280,000 left in current CIP 11 -27 which could be used to get
started with this project and do a detailed design until funding could be allocated for
the entire project. US -12 and US -27 could be taken off the list of unscheduled
projects and incorporated into this project.
ALTERNATIVES
Reduce the scope of work to:
1. Expanding the Children's Services area
2. Expanding the existing Community Room
The estimated project cost for this reduced scope is $1,020,000
Library CIP Proposal - February 27, 2014 1 City of Mountain View